246 Girard St
San Francisco permit 202304075307 · Portola
1st flr add 2-bedrm, 1-bath, 1-living rm, 2nd flr add 1-bath, infill below e 2nd flr at rear, infill lightwell not visible from any off site land, no change to bldg height or depth, lower e 1st flr by +/- 18", remove front & rear ext stairs, relocate front entry to 1st flr.
- Filed
- Apr 7, 2023
- Issued
- Aug 31, 2023 (5 months after filing)
- Completed
- Nov 21, 2025 (27 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2023 were typically issued within 1 month (median of 4,704 issued permits).
- Review stops
- 11 stops across 4 departments
- Comments issued
- Twice, by Fire Department
- Put on hold
- Once
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Apr 7, 2023 | Apr 7, 2023 | — |
Zoning review Planning · CP-ZOC | Apr 10, 2023 | Aug 9, 2023 | Approved |
Planning neighborhood notice Planning · CP-NP | Jun 15, 2023 | Jun 16, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Aug 14, 2023 | Aug 14, 2023 | Approved |
Structural plan approval Building Inspection · PAD-STR | Aug 14, 2023 | Aug 14, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 14, 2023 | Aug 14, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Aug 14, 2023 | Aug 14, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Aug 14, 2023 | Aug 14, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Aug 30, 2023 | Aug 30, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Aug 30, 2023 | Aug 30, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 31, 2023 | Aug 31, 2023 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $228,000
| Name | Role | License on permit |
|---|---|---|
| Man Yip Li Schaub Li Architects | Architect | C-39027 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2022