San Francisco permit 202304075314 · South of Market
Demo of (e)roofing assemblies: 2 private use decks, roof elevator penthouse, 3 penthouses. install n roofing assemblies: roof 4 private use decks, elevator penthouses, 3 penthouses. install n flashing trim copings, rwls, gutters, finishes to metal(e). reinstall e comc. pavers @ 4 deck areas
- Filed
- Apr 7, 2023
- Issued
- Aug 1, 2025 (28 months after filing)
- Completed
- Not completed yet
- Review stops
- 18 stops across 5 departments
- Comments issued
- None
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Apartment and hotel inspection Building Inspection · HIS | Apr 7, 2023 | Apr 7, 2023 | — |
Intake Building Inspection · INTAKE | Apr 7, 2023 | Apr 7, 2023 | — |
Zoning review Planning · CP-ZOC | Apr 14, 2023 | Sep 24, 2024 | Approved |
Permit Center Permit Center · PERMIT-CTR | Apr 17, 2023 | Apr 17, 2023 | — |
Building plan review Building Inspection · BLDG | Apr 27, 2023 | Apr 27, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Aug 9, 2023 | Aug 9, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Aug 9, 2023 | Aug 9, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 9, 2023 | Aug 9, 2023 | Approved |
Building plan review Building Inspection · BLDG | Sep 24, 2024 | Sep 24, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 24, 2024 | Sep 24, 2024 | Approved |
Intake Building Inspection · INTAKE | Apr 15, 2025 | Apr 15, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Apr 15, 2025 | Apr 15, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 22, 2025 | Apr 22, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jun 3, 2025 | Jun 3, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jun 3, 2025 | Jun 3, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Jun 5, 2025 | Jun 5, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Jun 26, 2025 | Jun 26, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 1, 2025 | Aug 1, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Issued
- Estimated cost
- $447,000
| Name | Role | License on permit |
|---|---|---|
| Sara Jane Cee Cee Architects | Architect | C25218 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2025