138 28th Av
San Francisco permit 202304145783 · Seacliff
Residential remodel of sfd including: infill existing lightwell and area below 2nd fl. add 2nd fl deck, convert 3rd fl roof to usable deck. full interior remodel including kitchen and add 1 new bathroom.
- Filed
- Apr 14, 2023
- Issued
- Sep 1, 2023 (5 months after filing)
- Completed
- Jan 5, 2026 (28 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 17 stops across 5 departments
- Comments issued
- None
- Put on hold
- Once
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Apr 14, 2023 | Apr 14, 2023 | — |
Zoning review Planning · CP-ZOC | Apr 18, 2023 | Apr 18, 2023 | — |
Zoning review Planning · CP-ZOC | Apr 28, 2023 | Apr 28, 2023 | — |
Building plan review Building Inspection · BLDG | May 4, 2023 | May 4, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | May 4, 2023 | May 4, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | May 12, 2023 | May 12, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | May 12, 2023 | May 12, 2023 | — |
Permit Center Permit Center · PERMIT-CTR | May 18, 2023 | May 18, 2023 | — |
Central Permit Bureau Building Inspection · CPB | May 23, 2023 | May 25, 2023 | — |
Structural plan approval Building Inspection · PAD-STR | May 25, 2023 | Jul 27, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Jun 30, 2023 | Jul 5, 2023 | — |
Structural plan approval Building Inspection · PAD-STR | Jul 31, 2023 | Jul 31, 2023 | Approved |
Building plan review Building Inspection · BLDG | Aug 1, 2023 | Aug 2, 2023 | Approved |
Building plan review Building Inspection · BLDG | Aug 2, 2023 | Aug 2, 2023 | Approved |
Zoning review Planning · CP-ZOC | Aug 2, 2023 | Aug 8, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Aug 9, 2023 | Aug 10, 2023 | Administrative |
Central Permit Bureau Building Inspection · CPB | Aug 10, 2023 | Sep 1, 2023 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $650,000
| Name | Role | License on permit |
|---|---|---|
| Richard Parker Hans Vaterlaus Acmr Architectural | Architect | C23212 |
| Albert Urrutia Atrium Structural Engineer | Engineer | S2994 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Nov 2017