605 Jackson St
San Francisco permit 202304185947 · Chinatown
Change of occupany from m to b. t.i. to drink shop: boba shop(to go only). interior remodel: electrical work for (n) equipment. plumbing work to (n) sinks, counter tops, entrance upgrade. (e) bldg does not have fire sprinklers system. front entry improvements.
- Filed
- Apr 18, 2023
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 22 stops across 7 departments
- Comments issued
- Twice, by Fire Department, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Apr 18, 2023 | May 8, 2023 | — |
Zoning review Planning · CP-ZOC | Apr 18, 2023 | Apr 18, 2023 | — |
Zoning review Planning · CP-ZOC | Apr 24, 2023 | Apr 24, 2023 | — |
Building plan review Building Inspection · BLDG | Apr 24, 2023 | Apr 24, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Apr 24, 2023 | Apr 24, 2023 | — |
Fire prevention review Fire Department · SFFD | Apr 24, 2023 | Apr 24, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Apr 24, 2023 | Apr 24, 2023 | — |
Public health review Public Health · HEALTH | Apr 24, 2023 | May 3, 2023 | — |
Electrical plan review Building Inspection · MECH-E | May 8, 2023 | May 8, 2023 | — |
Street use and mapping Public Works · DPW-BSM | May 8, 2023 | May 8, 2023 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | May 9, 2023 | May 9, 2023 | — |
Central Permit Bureau Building Inspection · CPB | May 10, 2023 | May 10, 2023 | — |
Fire prevention review Fire Department · SFFD | May 10, 2023 | May 17, 2023 | Approved |
Fire prevention review Fire Department · SFFD | May 17, 2023 | May 17, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Oct 5, 2023 | Oct 10, 2023 | Approved |
Building plan review Building Inspection · BLDG | Oct 11, 2023 | Oct 11, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 11, 2023 | Oct 18, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 18, 2023 | Oct 20, 2023 | Approved |
Zoning review Planning · CP-ZOC | Oct 20, 2023 | Oct 31, 2023 | Approved |
Public health review Public Health · HEALTH | Nov 1, 2023 | Nov 21, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Nov 21, 2023 | Nov 21, 2023 | Administrative |
Central Permit Bureau Building Inspection · CPB | Nov 21, 2023 | In progress | In Progress |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Withdrawn
- Estimated cost
- $45,000
| Name | Role | License on permit |
|---|---|---|
| Chong Hong | Architect | C84784 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026