160 10th St
San Francisco permit 202304185961 · South of Market
Change of use from existing commercial to single family residence. remove partial non-structural wall and provide new wall. variance application is required for open space #202210592prj.
- Filed
- Aug 18, 2026
- Issued
- Oct 28, 2026 (2 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2026 typically took 4 months to be issued (median of 245 issued permits).
- Review stops
- 24 stops across 5 departments
- Comments issued
- 7 times, by Planning, Permit Center, Building Inspection, Fire Department
- Put on hold
- Once
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Building inspector Building Inspection · BID-INSP | Apr 18, 2023 | Apr 18, 2023 | — |
Intake Building Inspection · INTAKE | Apr 18, 2023 | Apr 18, 2023 | — |
Zoning review Planning · CP-ZOC | Apr 19, 2023 | Oct 18, 2023 | Issued Comments |
Planning neighborhood notice Planning · CP-NP | Apr 26, 2023 | Oct 20, 2026 | Approved |
Zoning review Planning · CP-ZOC | Mar 11, 2026 | Mar 11, 2026 | Approved |
Permit Center Permit Center · PERMIT-CTR | Mar 16, 2026 | Apr 2, 2026 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Jun 10, 2026 | Jun 25, 2026 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Jul 28, 2026 | Aug 14, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 17, 2026 | Aug 18, 2026 | In Progress |
Zoning review Planning · CP-ZOC | Aug 18, 2026 | Aug 19, 2026 | Approved |
Building plan review Building Inspection · BLDG | Aug 18, 2026 | Sep 24, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 18, 2026 | Sep 1, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Aug 18, 2026 | Sep 10, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Aug 18, 2026 | Sep 3, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Aug 18, 2026 | Oct 21, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Oct 1, 2026 | Oct 5, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Oct 1, 2026 | Oct 13, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 1, 2026 | Oct 9, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Oct 1, 2026 | Oct 20, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 1, 2026 | Oct 5, 2026 | Approved |
Zoning review Planning · CP-ZOC | Oct 19, 2026 | Oct 19, 2026 | Approved |
Development fee collection Building Inspection · DFCU | Oct 21, 2026 | Oct 21, 2026 | Administrative |
Central Permit Bureau Building Inspection · CPB | Oct 21, 2026 | Oct 28, 2026 | Administrative |
Address verification Building Inspection · ADDR | Oct 26, 2026 | Oct 26, 2026 | Not Applicable |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $98,911
| Name | Role | License on permit |
|---|---|---|
| Marc Dimalanta D-Scheme Studio | Architect | C33350 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026