2685 California St
San Francisco permit 202304196063 · Pacific Heights
Proposed adu unit under state program w/ structural, plumbing & electrical work to comply w/ nov# 201711673.
- Filed
- Apr 19, 2023
- Issued
- May 31, 2024 (13 months after filing)
- Completed
- Apr 24, 2025 (11 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 29 stops across 5 departments
- Comments issued
- Once, by Public Utilities
- Put on hold
- 5 times
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Code enforcement Building Inspection · CES | Apr 19, 2023 | Apr 19, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Apr 19, 2023 | May 12, 2023 | — |
Zoning review Planning · CP-ZOC | May 12, 2023 | Jan 19, 2024 | Approved |
Building plan review Building Inspection · BLDG | May 12, 2023 | Jan 22, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 12, 2023 | Jul 19, 2023 | — |
Fire prevention review Fire Department · SFFD | May 12, 2023 | Sep 11, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | May 12, 2023 | May 15, 2023 | — |
Urban forestry Public Works · DPW-BUF | May 12, 2023 | Jun 13, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | May 12, 2023 | Jun 1, 2023 | — |
Permit Processing Center Building Inspection · PPC | May 12, 2023 | Mar 22, 2024 | Administrative |
Structural plan approval Building Inspection · PAD-STR | Jun 6, 2023 | Jul 20, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Jul 19, 2023 | Jul 19, 2023 | — |
Structural plan approval Building Inspection · PAD-STR | Jul 20, 2023 | Jul 20, 2023 | — |
Urban forestry Public Works · DPW-BUF | Sep 8, 2023 | Sep 8, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 8, 2023 | Sep 8, 2023 | Approved |
Structural plan approval Building Inspection · PAD-STR | Sep 8, 2023 | Sep 11, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 8, 2023 | Sep 19, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 8, 2023 | Sep 10, 2023 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Sep 11, 2023 | Sep 11, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 15, 2023 | Sep 21, 2023 | Approved |
Zoning review Planning · CP-ZOC | Jan 19, 2024 | Feb 28, 2024 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Mar 1, 2024 | Mar 5, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Mar 1, 2024 | Mar 4, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Mar 1, 2024 | Mar 1, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 1, 2024 | Mar 19, 2024 | Approved |
Urban forestry Public Works · DPW-BUF | Mar 1, 2024 | Mar 19, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 1, 2024 | Mar 5, 2024 | Approved |
Development fee collection Building Inspection · DFCU | Mar 21, 2024 | Mar 21, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | Mar 22, 2024 | May 31, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $118,000
| Name | Role | License on permit |
|---|---|---|
| Howard E Blecher Blecher Bldg & Urban Design | Architect | C36464 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026