1326 Guerrero St
San Francisco permit 202304216181 · Mission
Replace(e)brick foundation w/(n) concrete. garage+roof structural upgrade, level house@ rear. full crawlspace digout for(1)additional parking space, install interior stair from garage to main house. n basement w/ n bedroom suite. reno to kitchen & primary suite 2nd flr bath, replace 1 full. shoring.
- Filed
- Apr 21, 2023
- Issued
- Oct 27, 2023 (6 months after filing)
- Completed
- May 7, 2025 (18 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 19 stops across 5 departments
- Comments issued
- Once, by Building Inspection
- Put on hold
- Once
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Apr 21, 2023 | Apr 21, 2023 | — |
Zoning review Planning · CP-ZOC | Apr 24, 2023 | Apr 24, 2023 | — |
Intake Building Inspection · INTAKE | Apr 28, 2023 | Apr 28, 2023 | — |
Zoning review Planning · CP-ZOC | May 1, 2023 | May 1, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | May 3, 2023 | May 3, 2023 | — |
Street use and mapping Public Works · DPW-BSM | May 3, 2023 | May 3, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | May 16, 2023 | May 16, 2023 | — |
Building plan review Building Inspection · BLDG | May 17, 2023 | May 17, 2023 | — |
Street use and mapping Public Works · DPW-BSM | May 17, 2023 | May 17, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | May 17, 2023 | May 22, 2023 | — |
Zoning review Planning · CP-ZOC | May 22, 2023 | May 22, 2023 | — |
Zoning review Planning · CP-ZOC | May 22, 2023 | May 22, 2023 | — |
Central Permit Bureau Building Inspection · CPB | May 22, 2023 | May 23, 2023 | — |
Permit Center Permit Center · PERMIT-CTR | May 22, 2023 | May 22, 2023 | — |
Structural plan approval Building Inspection · PAD-STR | May 23, 2023 | Aug 25, 2023 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Sep 22, 2023 | Oct 11, 2023 | Approved |
Zoning review Planning · CP-ZOC | Oct 12, 2023 | Oct 17, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Oct 19, 2023 | Oct 20, 2023 | Administrative |
Central Permit Bureau Building Inspection · CPB | Oct 20, 2023 | Oct 27, 2023 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $864,205
| Name | Role | License on permit |
|---|---|---|
| Stephen G Verner Verner Architects | Architect | C34368 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026