135 Locust St
San Francisco permit 202304216262 · Presidio Heights
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
Revision to address nov 202305978. to revise quantity of demolition & structural details not previously captured under pa#202110070082. foundation replacement, 202112094048 bp, 202206075813 & rev 202208120480
- Filed
- Apr 21, 2023
- Issued
- Feb 27, 2024 (10 months after filing)
- Completed
- Feb 7, 2025 (11 months after issuance)
- Review stops
- 16 stops across 3 departments
- Comments issued
- 3 times, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Building inspector Building Inspection · BID-INSP | Apr 21, 2023 | Apr 21, 2023 | — |
Intake Building Inspection · INTAKE | Apr 21, 2023 | Apr 21, 2023 | — |
Zoning review Planning · CP-ZOC | Jun 28, 2023 | Nov 7, 2023 | Approved |
Planning neighborhood notice Planning · CP-NP | Sep 14, 2023 | Sep 22, 2023 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Nov 8, 2023 | Nov 8, 2023 | Not Applicable |
Permit Center Permit Center · PERMIT-CTR | Nov 9, 2023 | Nov 9, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Nov 10, 2023 | Nov 17, 2023 | Administrative |
Building pre-screening Building Inspection · PRE-BLDG | Nov 17, 2023 | Nov 17, 2023 | Approved |
Building plan review Building Inspection · BLDG | Nov 17, 2023 | Jan 29, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Nov 17, 2023 | Jan 31, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Jan 31, 2024 | Jan 31, 2024 | Administrative |
Structural plan approval Building Inspection · PAD-STR | Feb 5, 2024 | Feb 13, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Feb 20, 2024 | Feb 20, 2024 | Approved |
Building plan review Building Inspection · BLDG | Feb 21, 2024 | Feb 21, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Feb 22, 2024 | Feb 22, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | Feb 22, 2024 | Feb 27, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $100,000
| Name | Role | License on permit |
|---|---|---|
| Hans Rainer Baldauf Bcv Architects | Architect | C-22624 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Nov 2024