Horizontal rear addition to existing single family residence. remodel existing second and third floors. new rear deck.

Timeline
Key dates from the city record.
Filed
Apr 25, 2023
Issued
May 1, 2024 (12 months after filing)
Completed
Mar 27, 2026 (23 months after issuance)

For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
55 stops across 6 departments
Comments issued
14 times, by Building Inspection, Public Utilities, Fire Department, Public Works, Permit Center
Put on hold
Once

Main permit

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

May 2, 2023—

Zoning review

Planning · CP-ZOC

Dec 13, 2023Approved

Permit Processing Center

Building Inspection · PPC

Apr 18, 2024In Progress

Planning neighborhood notice

Planning · CP-NP

Oct 19, 2023Administrative

Building plan review

Building Inspection · BLDG

Jan 10, 2024Issued Comments

Street use and mapping

Public Works · DPW-BSM

Jan 3, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Dec 19, 2023Issued Comments

Building plan review

Building Inspection · BLDG

Feb 5, 2024Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Jan 29, 2024Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Jan 29, 2024Approved

Fire prevention review

Fire Department · SFFD

Feb 13, 2024Approved

Building plan review

Building Inspection · BLDG

Feb 22, 2024Approved

Zoning review

Planning · CP-ZOC

Feb 26, 2024Approved

Fire prevention review

Fire Department · SFFD

Feb 26, 2024Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Feb 27, 2024Approved

Fire prevention review

Fire Department · SFFD

Feb 28, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Mar 20, 2024Issued Comments

Zoning review

Planning · CP-ZOC

Feb 29, 2024Approved

Building plan review

Building Inspection · BLDG

Feb 29, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Feb 27, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Apr 3, 2024Approved-Stipulated

Zoning review

Planning · CP-ZOC

Apr 3, 2024Approved

Building plan review

Building Inspection · BLDG

Apr 5, 2024Approved

Fire prevention review

Fire Department · SFFD

Apr 9, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Apr 8, 2024Approved

Central Permit Bureau

Building Inspection · CPB

May 1, 2024Administrative

Addendum 1: Foundation,struct,arch,t-24,final

Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Jun 3, 2024Issued Comments

Electrical pre-screening

Building Inspection · PRE-MECH-E

May 23, 2024Not Applicable

Building pre-screening

Building Inspection · PRE-BLDG

May 24, 2024Approved

Mechanical pre-screening

Building Inspection · PRE-MECH

Jun 3, 2024Issued Comments

Permit Center

Permit Center · PERMIT-CTR

Jun 10, 2024Approved

Mechanical pre-screening

Building Inspection · PRE-MECH

Jun 10, 2024Approved

Central Permit Bureau

Building Inspection · CPB

Jun 12, 2024Administrative

Building plan review

Building Inspection · BLDG

Jul 24, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Jul 26, 2024Issued Comments

Fire prevention review

Fire Department · SFFD

Jul 29, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Jun 25, 2024Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Jun 18, 2024Approved

Permit Processing Center

Building Inspection · PPC

Jan 10, 2025Administrative

Building plan review

Building Inspection · BLDG

Sep 24, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Oct 10, 2024Issued Comments

Building plan review

Building Inspection · BLDG

Oct 11, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Oct 11, 2024Approved

Building plan review

Building Inspection · BLDG

Oct 15, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Dec 13, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

Dec 13, 2024Approved

Fire prevention review

Fire Department · SFFD

Dec 19, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Dec 17, 2024Approved

Building plan review

Building Inspection · BLDG

Dec 27, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

Jan 2, 2025Approved

Fire prevention review

Fire Department · SFFD

Dec 31, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Jan 2, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jan 6, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Jan 14, 2025Administrative

Zoning review

Planning · CP-ZOC

Jan 10, 2025Approved

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$596,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Heidi Lee Liebes

Lieves Architects

ArchitectC29300
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202304256381 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record