1651 09th Av
San Francisco permit 202304256381 · Inner Sunset
Horizontal rear addition to existing single family residence. remodel existing second and third floors. new rear deck.
- Filed
- Apr 25, 2023
- Issued
- May 1, 2024 (12 months after filing)
- Completed
- Mar 27, 2026 (23 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 55 stops across 6 departments
- Comments issued
- 14 times, by Building Inspection, Public Utilities, Fire Department, Public Works, Permit Center
- Put on hold
- Once
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Apr 25, 2023 | May 2, 2023 | — |
Zoning review Planning · CP-ZOC | May 2, 2023 | Dec 13, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | May 2, 2023 | Apr 18, 2024 | In Progress |
Planning neighborhood notice Planning · CP-NP | Oct 6, 2023 | Oct 19, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Dec 13, 2023 | Jan 10, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Dec 13, 2023 | Jan 3, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 13, 2023 | Dec 19, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Jan 24, 2024 | Feb 5, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jan 29, 2024 | Jan 29, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jan 29, 2024 | Jan 29, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Feb 5, 2024 | Feb 13, 2024 | Approved |
Building plan review Building Inspection · BLDG | Feb 20, 2024 | Feb 22, 2024 | Approved |
Zoning review Planning · CP-ZOC | Feb 23, 2024 | Feb 26, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Feb 23, 2024 | Feb 26, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Feb 23, 2024 | Feb 27, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Feb 27, 2024 | Feb 28, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 27, 2024 | Mar 20, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Feb 27, 2024 | Feb 29, 2024 | Approved |
Building plan review Building Inspection · BLDG | Feb 27, 2024 | Feb 29, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 27, 2024 | Feb 27, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Apr 3, 2024 | Apr 3, 2024 | Approved-Stipulated |
Zoning review Planning · CP-ZOC | Apr 3, 2024 | Apr 3, 2024 | Approved |
Building plan review Building Inspection · BLDG | Apr 3, 2024 | Apr 5, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Apr 3, 2024 | Apr 9, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 3, 2024 | Apr 8, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 18, 2024 | May 1, 2024 | Administrative |
Addendum 1: Foundation,struct,arch,t-24,final
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | May 22, 2024 | Jun 3, 2024 | Issued Comments |
Electrical pre-screening Building Inspection · PRE-MECH-E | May 23, 2024 | May 23, 2024 | Not Applicable |
Building pre-screening Building Inspection · PRE-BLDG | May 24, 2024 | May 24, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Jun 3, 2024 | Jun 3, 2024 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Jun 3, 2024 | Jun 10, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Jun 10, 2024 | Jun 10, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 12, 2024 | Jun 12, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Jun 12, 2024 | Jul 24, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jun 12, 2024 | Jul 26, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jun 12, 2024 | Jul 29, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jun 12, 2024 | Jun 25, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jun 12, 2024 | Jun 18, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Jun 12, 2024 | Jan 10, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Sep 23, 2024 | Sep 24, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Oct 10, 2024 | Oct 10, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Oct 11, 2024 | Oct 11, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Oct 11, 2024 | Oct 11, 2024 | Approved |
Building plan review Building Inspection · BLDG | Oct 15, 2024 | Oct 15, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 13, 2024 | Dec 13, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Dec 13, 2024 | Dec 13, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Dec 13, 2024 | Dec 19, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 13, 2024 | Dec 17, 2024 | Approved |
Building plan review Building Inspection · BLDG | Dec 24, 2024 | Dec 27, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Dec 24, 2024 | Jan 2, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Dec 24, 2024 | Dec 31, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 24, 2024 | Jan 2, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 24, 2024 | Jan 6, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 6, 2025 | Jan 14, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Jan 9, 2025 | Jan 10, 2025 | Approved |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $596,000
| Name | Role | License on permit |
|---|---|---|
| Heidi Lee Liebes Lieves Architects | Architect | C29300 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2015