Commercial or tenant improvementFull plan reviewIssued
Street view · Sep 2026
Google Street View of 1520 Pacific Av, Sep 2026
Scope of work
As written on the permit application.

Change of use from b to i-4. new child care facility @ e vacant medical office.

Timeline
Key dates from the city record.
Filed
Apr 27, 2023
Issued
Dec 14, 2023 (8 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
23 stops across 6 departments
Comments issued
7 times, by Building Inspection, Fire Department, Public Utilities
Put on hold
Once
Review stopFinishedResult

Intake

Building Inspection · INTAKE

Apr 27, 2023—

Zoning review

Planning · CP-ZOC

Apr 27, 2023—

Permit Center

Permit Center · PERMIT-CTR

Apr 28, 2023—

Central Permit Bureau

Building Inspection · CPB

May 9, 2023—

Building plan review

Building Inspection · BLDG

Jun 15, 2023Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Jul 21, 2023Approved

Fire prevention review

Fire Department · SFFD

Jul 26, 2023Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Aug 24, 2023Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Aug 25, 2023Issued Comments

Street use and mapping

Public Works · DPW-BSM

Sep 7, 2023Approved

Building plan review

Building Inspection · BLDG

Sep 15, 2023Issued Comments

Building plan review

Building Inspection · BLDG

Oct 6, 2023Issued Comments

Building plan review

Building Inspection · BLDG

Oct 26, 2023Approved

Structural plan approval

Building Inspection · PAD-STR

Nov 21, 2023Issued Comments

Fire prevention review

Fire Department · SFFD

Nov 3, 2023Approved

Public Utilities Commission review

Public Utilities · SFPUC

Nov 3, 2023Approved

Mechanical and energy plan review

Building Inspection · MECH

Nov 6, 2023Approved

Street use and mapping

Public Works · DPW-BSM

Nov 13, 2023Approved

Zoning review

Planning · CP-ZOC

Nov 15, 2023Approved

Structural plan approval

Building Inspection · PAD-STR

Dec 6, 2023Approved

Permit Processing Center

Building Inspection · PPC

Dec 8, 2023Administrative

Central Permit Bureau

Building Inspection · CPB

Dec 14, 2023Administrative

Development fee collection

Building Inspection · DFCU

Dec 11, 2023Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$165,500
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Julio Cesar Guerrero

Guerrero Design

ArchitectC38612
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202304276652 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record