528 Bryant St
San Francisco permit 202304286756 · South of Market
Change of land use from sales & service, nonretail - wholesale to office. building renovation for change of use including; alteration of facade for transparency by new glazing for lobby entry, (e) garage door to remain as loading area, interior demarkation of lobby from office space #1 with half ...
- Filed
- Apr 28, 2023
- Issued
- May 21, 2024 (13 months after filing)
- Completed
- Apr 25, 2025 (11 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 31 stops across 5 departments
- Comments issued
- 7 times, by Building Inspection, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Apr 28, 2023 | May 1, 2023 | Administrative |
Permit Processing Center Building Inspection · PPC | May 1, 2023 | May 14, 2024 | Administrative |
Zoning review Planning · CP-ZOC | May 2, 2023 | Nov 8, 2023 | Approved |
Planning neighborhood notice Planning · CP-NP | Sep 11, 2023 | Sep 25, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Nov 8, 2023 | Dec 22, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Nov 8, 2023 | Dec 29, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Nov 8, 2023 | Jan 19, 2024 | Administrative |
Street use and mapping Public Works · DPW-BSM | Nov 8, 2023 | Nov 13, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Nov 8, 2023 | Dec 8, 2023 | Approved |
Building plan review Building Inspection · BLDG | Mar 11, 2024 | Mar 12, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Mar 25, 2024 | Mar 25, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Mar 27, 2024 | Apr 9, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Mar 28, 2024 | Apr 2, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 28, 2024 | Apr 12, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Mar 28, 2024 | Apr 1, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 4, 2024 | Apr 4, 2024 | Approved |
Zoning review Planning · CP-ZOC | Apr 4, 2024 | Apr 4, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 4, 2024 | Apr 9, 2024 | Approved |
Zoning review Planning · CP-ZOC | Apr 10, 2024 | Apr 10, 2024 | Approved |
Building plan review Building Inspection · BLDG | Apr 10, 2024 | Apr 10, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 10, 2024 | Apr 12, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 10, 2024 | Apr 11, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Apr 12, 2024 | Apr 12, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Apr 12, 2024 | Apr 23, 2024 | Approved |
Zoning review Planning · CP-ZOC | Apr 12, 2024 | Apr 15, 2024 | Approved |
Building plan review Building Inspection · BLDG | Apr 12, 2024 | Apr 18, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 12, 2024 | Apr 17, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Apr 24, 2024 | Apr 25, 2024 | Administrative |
Fire prevention review Fire Department · SFFD | Apr 25, 2024 | Apr 25, 2024 | Administrative |
Development fee collection Building Inspection · DFCU | Apr 25, 2024 | May 13, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | May 14, 2024 | May 21, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $58,000
| Name | Role | License on permit |
|---|---|---|
| James William Zack Zack/Devito Architecture | Architect | C24446 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026