272 Hartford St
San Francisco permit 202304296759 · Castro/Upper Market
Comply with dbi internal audit nov#2023-05733 for work exceeding scope of approved permit applications #2014-0124-7050 & #2014-1224-4273. rebuild exterior stairs from basement to 1st floor.
- Filed
- Mar 31, 2026
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 19 stops across 4 departments
- Comments issued
- 6 times, by Building Inspection, Fire Department
- Put on hold
- Once
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Building inspector Building Inspection · BID-INSP | Apr 29, 2023 | May 2, 2023 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Apr 29, 2023 | May 1, 2023 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Aug 21, 2023 | Aug 21, 2023 | Not Applicable |
Building inspector Building Inspection · BID-INSP | Nov 8, 2023 | Nov 8, 2023 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Jan 23, 2026 | Jan 23, 2026 | Approved |
Permit Center Permit Center · PERMIT-CTR | Mar 4, 2026 | Mar 25, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 31, 2026 | Mar 31, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Mar 31, 2026 | Mar 31, 2026 | Approved |
Building plan review Building Inspection · BLDG | Mar 31, 2026 | May 12, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Mar 31, 2026 | Apr 24, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Mar 31, 2026 | Jul 31, 2026 | Issued Comments |
Building inspector Building Inspection · BID-INSP | Mar 31, 2026 | In progress | — |
Permit Processing Center Building Inspection · PPC | Mar 31, 2026 | In progress | — |
Building plan review Building Inspection · BLDG | Sep 10, 2026 | Sep 10, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Oct 20, 2026 | Oct 20, 2026 | Approved |
Building plan review Building Inspection · BLDG | Oct 22, 2026 | Oct 22, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | — | In progress | — |
Mechanical and energy plan review Building Inspection · MECH | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Filed
- Estimated cost
- $15,000
| Name | Role | License on permit |
|---|---|---|
| Jeremiah W P Schaub Schaub | Li | Architects | Architect | C-32289 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025