CheckMyDesigner

1964 Post St #0

San Francisco permit 202305016787 · Japantown

ADUFull plan reviewIssued
Street view · Sep 2026
Google Street View of 1964 Post St #0, Sep 2026
Scope of work
As written on the permit application.

Add two (2) new adu to the ground floor of the building under ordinance 162-16.

Timeline
Key dates from the city record.
Filed
May 1, 2023
Issued
May 31, 2024 (13 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
21 stops across 5 departments
Comments issued
4 times, by Building Inspection
Put on hold
Twice
Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

May 2, 2023—

Zoning review

Planning · CP-ZOC

Jul 26, 2023Administrative

Structural plan approval

Building Inspection · PAD-STR

Sep 25, 2023Issued Comments

Building plan review

Building Inspection · BLDG

Sep 26, 2023Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Nov 6, 2023Issued Comments

Fire prevention review

Fire Department · SFFD

May 10, 2023—

Street use and mapping

Public Works · DPW-BSM

May 4, 2023—

Public Utilities Commission review

Public Utilities · SFPUC

May 23, 2023—

Development fee collection

Building Inspection · DFCU

Apr 18, 2024Administrative

Permit Processing Center

Building Inspection · PPC

Apr 19, 2024—

Street use and mapping

Public Works · DPW-BSM

Sep 28, 2023Approved

Mechanical and energy plan review

Building Inspection · MECH

Nov 6, 2023Issued Comments

Building plan review

Building Inspection · BLDG

Nov 21, 2023Approved

Mechanical and energy plan review

Building Inspection · MECH

Nov 14, 2023Approved

Fire prevention review

Fire Department · SFFD

Nov 16, 2023Approved

Public Utilities Commission review

Public Utilities · SFPUC

Nov 17, 2023Approved

Zoning review

Planning · CP-ZOC

Apr 12, 2024Approved

Structural plan approval

Building Inspection · PAD-STR

Dec 11, 2023Approved

Street use and mapping

Public Works · DPW-BSM

Nov 28, 2023Approved

Central Permit Bureau

Building Inspection · CPB

May 31, 2024Administrative

Public Utilities Commission review

Public Utilities · SFPUC

Sep 26, 2023Approved

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$357,536
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Mark Kevin Hogan

Openscope Studio

ArchitectC33268
Ali Afrasiabi

Rei Buildup

EngineerS5413
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202305016787 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record