1964 Post St #0
San Francisco permit 202305016787 · Japantown
Add two (2) new adu to the ground floor of the building under ordinance 162-16.
- Filed
- May 1, 2023
- Issued
- May 31, 2024 (13 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 21 stops across 5 departments
- Comments issued
- 4 times, by Building Inspection
- Put on hold
- Twice
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 1, 2023 | May 2, 2023 | — |
Zoning review Planning · CP-ZOC | May 3, 2023 | Jul 26, 2023 | Administrative |
Structural plan approval Building Inspection · PAD-STR | May 3, 2023 | Sep 25, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | May 3, 2023 | Sep 26, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | May 3, 2023 | Nov 6, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | May 3, 2023 | May 10, 2023 | — |
Street use and mapping Public Works · DPW-BSM | May 3, 2023 | May 4, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | May 3, 2023 | May 23, 2023 | — |
Development fee collection Building Inspection · DFCU | May 3, 2023 | Apr 18, 2024 | Administrative |
Permit Processing Center Building Inspection · PPC | May 3, 2023 | Apr 19, 2024 | — |
Street use and mapping Public Works · DPW-BSM | Sep 28, 2023 | Sep 28, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Nov 6, 2023 | Nov 6, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Nov 14, 2023 | Nov 21, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Nov 14, 2023 | Nov 14, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Nov 14, 2023 | Nov 16, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 14, 2023 | Nov 17, 2023 | Approved |
Zoning review Planning · CP-ZOC | Nov 21, 2023 | Apr 12, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Nov 21, 2023 | Dec 11, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 21, 2023 | Nov 28, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 19, 2024 | May 31, 2024 | Administrative |
Public Utilities Commission review Public Utilities · SFPUC | — | Sep 26, 2023 | Approved |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $357,536
| Name | Role | License on permit |
|---|---|---|
| Mark Kevin Hogan Openscope Studio | Architect | C33268 |
| Ali Afrasiabi Rei Buildup | Engineer | S5413 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026