San Francisco permit 202305026865 · South of Market

Commercial or tenant improvement (type unconfirmed)Full plan reviewIssued
Street view · Sep 2026
Google Street View of 150 09th St, Sep 2026
Scope of work
As written on the permit application.

Mayor dir 13-01. 100% affordable housing. comprehensive alterations, upgrades, & repairs to (e) el dorado res. hotel/(e) sro 4-story 57 units to increase to 62 residential public housing sleeping units.

Timeline
Key dates from the city record.
Filed
May 2, 2023
Issued
Apr 3, 2024 (11 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
104 stops across 7 departments
Comments issued
34 times, by Public Utilities, Public Health, Fire Department, Building Inspection, Public Works, Permit Center
Put on hold
Once

Main permit

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

May 8, 2023—

Apartment and hotel inspection

Building Inspection · HIS

May 5, 2023—

Permit Processing Center

Building Inspection · PPC

Apr 2, 2024—

Zoning review

Planning · CP-ZOC

Aug 1, 2023Approved

Building plan review

Building Inspection · BLDG

Aug 8, 2023Administrative

Public Utilities Commission review

Public Utilities · SFPUC

Aug 18, 2023Issued Comments

Street use and mapping

Public Works · DPW-BSM

Aug 3, 2023Approved-Stipulated

Public health review

Public Health · HEALTH

Aug 25, 2023Issued Comments

Public health food review

Public Health · HEALTH-FD

Sep 5, 2023Administrative

Public health review

Public Health · HEALTH

Sep 5, 2023Administrative

Fire prevention review

Fire Department · SFFD

Feb 15, 2024Issued Comments

Building plan review

Building Inspection · BLDG

Feb 26, 2024Issued Comments

Zoning review

Planning · CP-ZOC

Feb 27, 2024Approved

Building plan review

Building Inspection · BLDG

Feb 28, 2024Administrative

Building plan review

Building Inspection · BLDG

Mar 26, 2024Approved

Fire prevention review

Fire Department · SFFD

Mar 28, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Mar 29, 2024Approved

Fire prevention review

Fire Department · SFFD

Apr 2, 2024Approved

Zoning review

Planning · CP-ZOC

Apr 1, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Apr 2, 2024Approved-Stipulated

Building plan review quality control

Building Inspection · BLDG-QC

Apr 1, 2024Administrative

Development fee collection

Building Inspection · DFCU

Apr 1, 2024Administrative

Public health review

Public Health · HEALTH

Apr 2, 2024Administrative

Central Permit Bureau

Building Inspection · CPB

Apr 3, 2024Administrative

Addendum 1: Foundation

Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Apr 9, 2024Approved

Building pre-screening

Building Inspection · PRE-BLDG

Apr 5, 2024Approved

Mechanical pre-screening

Building Inspection · PRE-MECH

Apr 5, 2024Not Applicable

Electrical pre-screening

Building Inspection · PRE-MECH-E

Apr 5, 2024Not Applicable

Central Permit Bureau

Building Inspection · CPB

Apr 9, 2024Administrative

Building plan review

Building Inspection · BLDG

Apr 15, 2024Issued Comments

Street use and mapping

Public Works · DPW-BSM

Apr 9, 2024Issued Comments

Permit Processing Center

Building Inspection · PPC

Apr 24, 2024—

Building plan review

Building Inspection · BLDG

Apr 22, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Apr 24, 2024Approved

Central Permit Bureau

Building Inspection · CPB

May 7, 2024Administrative

Addendum 2: Arch,remaining structural,mep,fire escapes

Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Apr 26, 2024Issued Comments

Electrical pre-screening

Building Inspection · PRE-MECH-E

Apr 24, 2024Approved

Building pre-screening

Building Inspection · PRE-BLDG

Apr 25, 2024Approved

Mechanical pre-screening

Building Inspection · PRE-MECH

Apr 26, 2024Issued Comments

Permit Center

Permit Center · PERMIT-CTR

May 6, 2024Approved

Mechanical pre-screening

Building Inspection · PRE-MECH

May 3, 2024Approved

Central Permit Bureau

Building Inspection · CPB

May 7, 2024Administrative

Building plan review

Building Inspection · BLDG

May 28, 2024Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Jun 26, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

May 17, 2024Issued Comments

Fire prevention review

Fire Department · SFFD

May 23, 2024Issued Comments

Street use and mapping

Public Works · DPW-BSM

May 8, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

May 8, 2024Approved

Public health review

Public Health · HEALTH

May 7, 2024Administrative

Permit Processing Center

Building Inspection · PPC

Sep 13, 2024Administrative

Electrical plan review

Building Inspection · MECH-E

May 23, 2024Issued Comments

Electrical plan review

Building Inspection · MECH-E

Jul 11, 2024Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Aug 5, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Aug 12, 2024Approved

Electrical plan review

Building Inspection · MECH-E

Aug 9, 2024Issued Comments

Building plan review

Building Inspection · BLDG

Aug 12, 2024Issued Comments

Fire prevention review

Fire Department · SFFD

Aug 8, 2024Issued Comments

Fire prevention review

Fire Department · SFFD

Aug 19, 2024Issued Comments

Electrical plan review

Building Inspection · MECH-E

Aug 27, 2024Issued Comments

Fire prevention review

Fire Department · SFFD

Aug 29, 2024Approved

Structural plan approval

Building Inspection · PAD-STR

Sep 5, 2024Approved

Electrical plan review

Building Inspection · MECH-E

Aug 30, 2024Approved

Building plan review

Building Inspection · BLDG

Sep 3, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

Sep 10, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Sep 11, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Sep 13, 2024Approved

Central Permit Bureau

Building Inspection · CPB

Sep 16, 2024Administrative

Addendum 3: Fire sprinklers

Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Jul 30, 2024Issued Comments

Central Permit Bureau

Building Inspection · CPB

Aug 6, 2024Administrative

Building pre-screening

Building Inspection · PRE-BLDG

Jul 29, 2024Issued Comments

Permit Center

Permit Center · PERMIT-CTR

Aug 6, 2024Approved

Building pre-screening

Building Inspection · PRE-BLDG

Aug 3, 2024Approved

Fire prevention review

Fire Department · SFFD

Aug 13, 2024Issued Comments

Permit Processing Center

Building Inspection · PPC

May 9, 2025Administrative

Fire prevention review

Fire Department · SFFD

Oct 29, 2024Issued Comments

Fire prevention review

Fire Department · SFFD

Jan 21, 2025Issued Comments

Fire prevention review

Fire Department · SFFD

Apr 17, 2025Issued Comments

Fire prevention review

Fire Department · SFFD

May 9, 2025Approved

Central Permit Bureau

Building Inspection · CPB

May 14, 2025Administrative

Addendum 4: Fire alarm & two-way communication

Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Aug 6, 2024Issued Comments

Building pre-screening

Building Inspection · PRE-BLDG

Aug 3, 2024Approved

Permit Center

Permit Center · PERMIT-CTR

Sep 30, 2024Approved

Building pre-screening

Building Inspection · PRE-BLDG

Sep 24, 2024Approved

Central Permit Bureau

Building Inspection · CPB

Sep 30, 2024Administrative

Fire prevention review

Fire Department · SFFD

Oct 28, 2024Issued Comments

Permit Processing Center

Building Inspection · PPC

Nov 12, 2025Administrative

Fire prevention review

Fire Department · SFFD

Jun 25, 2025Issued Comments

Fire prevention review

Fire Department · SFFD

Sep 29, 2025Issued Comments

Fire prevention review

Fire Department · SFFD

Oct 22, 2025Issued Comments

Fire prevention review

Fire Department · SFFD

Nov 3, 2025Approved-Stipulated

Central Permit Bureau

Building Inspection · CPB

Nov 17, 2025Administrative

Addendum 5: Transformer vault retaining wall

Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Oct 9, 2024Issued Comments

Building pre-screening

Building Inspection · PRE-BLDG

Oct 3, 2024Approved

Permit Center

Permit Center · PERMIT-CTR

Oct 23, 2024Approved

Building pre-screening

Building Inspection · PRE-BLDG

Oct 18, 2024Approved

Central Permit Bureau

Building Inspection · CPB

Oct 23, 2024Administrative

Building plan review

Building Inspection · BLDG

Nov 1, 2024Issued Comments

Fire prevention review

Fire Department · SFFD

Oct 25, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Oct 28, 2024Issued Comments

Permit Processing Center

Building Inspection · PPC

Jan 9, 2025Administrative

Building plan review

Building Inspection · BLDG

Nov 21, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Jan 8, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Jan 23, 2025Administrative

Addendum 6: Errcs

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Feb 27, 2026Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$9,116,167
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Daniel M Levine

The John Stewart Company

ArchitectC10154
David Benjamin Yadegar

David Yadegar, Pe

EngineerC-73922
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202305026865 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record