150 09th St
San Francisco permit 202305026865 · South of Market
Mayor dir 13-01. 100% affordable housing. comprehensive alterations, upgrades, & repairs to (e) el dorado res. hotel/(e) sro 4-story 57 units to increase to 62 residential public housing sleeping units.
- Filed
- May 2, 2023
- Issued
- Apr 3, 2024 (11 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 104 stops across 7 departments
- Comments issued
- 34 times, by Public Utilities, Public Health, Fire Department, Building Inspection, Public Works, Permit Center
- Put on hold
- Once
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 2, 2023 | May 8, 2023 | — |
Apartment and hotel inspection Building Inspection · HIS | May 5, 2023 | May 5, 2023 | — |
Permit Processing Center Building Inspection · PPC | May 8, 2023 | Apr 2, 2024 | — |
Zoning review Planning · CP-ZOC | May 9, 2023 | Aug 1, 2023 | Approved |
Building plan review Building Inspection · BLDG | Aug 2, 2023 | Aug 8, 2023 | Administrative |
Public Utilities Commission review Public Utilities · SFPUC | Aug 2, 2023 | Aug 18, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Aug 2, 2023 | Aug 3, 2023 | Approved-Stipulated |
Public health review Public Health · HEALTH | Aug 2, 2023 | Aug 25, 2023 | Issued Comments |
Public health food review Public Health · HEALTH-FD | Sep 5, 2023 | Sep 5, 2023 | Administrative |
Public health review Public Health · HEALTH | Sep 5, 2023 | Sep 5, 2023 | Administrative |
Fire prevention review Fire Department · SFFD | Feb 15, 2024 | Feb 15, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Feb 16, 2024 | Feb 26, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Feb 27, 2024 | Feb 27, 2024 | Approved |
Building plan review Building Inspection · BLDG | Feb 28, 2024 | Feb 28, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Mar 26, 2024 | Mar 26, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Mar 28, 2024 | Mar 28, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 29, 2024 | Mar 29, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Apr 1, 2024 | Apr 2, 2024 | Approved |
Zoning review Planning · CP-ZOC | Apr 1, 2024 | Apr 1, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Apr 1, 2024 | Apr 2, 2024 | Approved-Stipulated |
Building plan review quality control Building Inspection · BLDG-QC | Apr 1, 2024 | Apr 1, 2024 | Administrative |
Development fee collection Building Inspection · DFCU | Apr 1, 2024 | Apr 1, 2024 | Administrative |
Public health review Public Health · HEALTH | Apr 2, 2024 | Apr 2, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | Apr 2, 2024 | Apr 3, 2024 | Administrative |
Addendum 1: Foundation
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Apr 3, 2024 | Apr 9, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Apr 5, 2024 | Apr 5, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Apr 5, 2024 | Apr 5, 2024 | Not Applicable |
Electrical pre-screening Building Inspection · PRE-MECH-E | Apr 5, 2024 | Apr 5, 2024 | Not Applicable |
Central Permit Bureau Building Inspection · CPB | Apr 9, 2024 | Apr 9, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Apr 9, 2024 | Apr 15, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Apr 9, 2024 | Apr 9, 2024 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Apr 9, 2024 | Apr 24, 2024 | — |
Building plan review Building Inspection · BLDG | Apr 18, 2024 | Apr 22, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Apr 24, 2024 | Apr 24, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 24, 2024 | May 7, 2024 | Administrative |
Addendum 2: Arch,remaining structural,mep,fire escapes
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Apr 19, 2024 | Apr 26, 2024 | Issued Comments |
Electrical pre-screening Building Inspection · PRE-MECH-E | Apr 24, 2024 | Apr 24, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Apr 25, 2024 | Apr 25, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Apr 26, 2024 | Apr 26, 2024 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Apr 29, 2024 | May 6, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | May 3, 2024 | May 3, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | May 7, 2024 | May 7, 2024 | Administrative |
Building plan review Building Inspection · BLDG | May 7, 2024 | May 28, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | May 7, 2024 | Jun 26, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | May 7, 2024 | May 17, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | May 7, 2024 | May 23, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | May 7, 2024 | May 8, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 7, 2024 | May 8, 2024 | Approved |
Public health review Public Health · HEALTH | May 7, 2024 | May 7, 2024 | Administrative |
Permit Processing Center Building Inspection · PPC | May 7, 2024 | Sep 13, 2024 | Administrative |
Electrical plan review Building Inspection · MECH-E | May 10, 2024 | May 23, 2024 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Jul 5, 2024 | Jul 11, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Aug 5, 2024 | Aug 5, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 5, 2024 | Aug 12, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Aug 5, 2024 | Aug 9, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Aug 8, 2024 | Aug 12, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Aug 8, 2024 | Aug 8, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Aug 19, 2024 | Aug 19, 2024 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Aug 26, 2024 | Aug 27, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Aug 29, 2024 | Aug 29, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Aug 30, 2024 | Sep 5, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Aug 30, 2024 | Aug 30, 2024 | Approved |
Building plan review Building Inspection · BLDG | Sep 3, 2024 | Sep 3, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 9, 2024 | Sep 10, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 9, 2024 | Sep 11, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 9, 2024 | Sep 13, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 13, 2024 | Sep 16, 2024 | Administrative |
Addendum 3: Fire sprinklers
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jul 19, 2024 | Jul 30, 2024 | Issued Comments |
Central Permit Bureau Building Inspection · CPB | Jul 23, 2024 | Aug 6, 2024 | Administrative |
Building pre-screening Building Inspection · PRE-BLDG | Jul 29, 2024 | Jul 29, 2024 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Jul 31, 2024 | Aug 6, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Aug 3, 2024 | Aug 3, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Aug 6, 2024 | Aug 13, 2024 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Aug 6, 2024 | May 9, 2025 | Administrative |
Fire prevention review Fire Department · SFFD | Oct 3, 2024 | Oct 29, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jan 13, 2025 | Jan 21, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Apr 17, 2025 | Apr 17, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | May 9, 2025 | May 9, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | May 9, 2025 | May 14, 2025 | Administrative |
Addendum 4: Fire alarm & two-way communication
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jul 31, 2024 | Aug 6, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Aug 3, 2024 | Aug 3, 2024 | Approved |
Permit Center Permit Center · PERMIT-CTR | Sep 18, 2024 | Sep 30, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Sep 24, 2024 | Sep 24, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 30, 2024 | Sep 30, 2024 | Administrative |
Fire prevention review Fire Department · SFFD | Oct 1, 2024 | Oct 28, 2024 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Oct 1, 2024 | Nov 12, 2025 | Administrative |
Fire prevention review Fire Department · SFFD | Jun 23, 2025 | Jun 25, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Sep 4, 2025 | Sep 29, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Oct 2, 2025 | Oct 22, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Nov 3, 2025 | Nov 3, 2025 | Approved-Stipulated |
Central Permit Bureau Building Inspection · CPB | Nov 12, 2025 | Nov 17, 2025 | Administrative |
Addendum 5: Transformer vault retaining wall
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Sep 24, 2024 | Oct 9, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Oct 3, 2024 | Oct 3, 2024 | Approved |
Permit Center Permit Center · PERMIT-CTR | Oct 10, 2024 | Oct 23, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Oct 18, 2024 | Oct 18, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 23, 2024 | Oct 23, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Oct 23, 2024 | Nov 1, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Oct 23, 2024 | Oct 25, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Oct 23, 2024 | Oct 28, 2024 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Oct 23, 2024 | Jan 9, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Nov 21, 2024 | Nov 21, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 8, 2025 | Jan 8, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 9, 2025 | Jan 23, 2025 | Administrative |
Addendum 6: Errcs
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Feb 27, 2026 | Feb 27, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $9,116,167
| Name | Role | License on permit |
|---|---|---|
| Daniel M Levine The John Stewart Company | Architect | C10154 |
| David Benjamin Yadegar David Yadegar, Pe | Engineer | C-73922 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026