851 California St
San Francisco permit 202305037008 · Nob Hill
Like for like remodel of (e) 15 guest bathrooms and upgrade one of them to bathroom rooom "351"is being modified to comply with ada requirements including roll-in shower. and "egvilanet facilitioan to elevator
- Filed
- May 3, 2023
- Issued
- May 16, 2023 (within 1 month of filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2023 were typically issued within 1 month (median of 4,704 issued permits).
- Review stops
- 9 stops across 3 departments
- Comments issued
- Not recorded for this permit
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Building inspector Building Inspection · BID-INSP | May 2, 2023 | May 2, 2023 | — |
Intake Building Inspection · INTAKE | May 3, 2023 | May 3, 2023 | — |
Building plan review Building Inspection · BLDG | May 3, 2023 | May 3, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | May 3, 2023 | May 3, 2023 | — |
Building plan review Building Inspection · BLDG | May 8, 2023 | May 8, 2023 | — |
Fire prevention review Fire Department · SFFD | May 9, 2023 | May 9, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | May 9, 2023 | May 9, 2023 | — |
Structural plan approval Building Inspection · PAD-STR | May 10, 2023 | May 10, 2023 | — |
Central Permit Bureau Building Inspection · CPB | May 16, 2023 | May 16, 2023 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Issued
- Estimated cost
- $160,000
| Name | Role | License on permit |
|---|---|---|
| Cory Steven Creath Axis Architectural | Architect | C18505 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026