1455 12th Av
San Francisco permit 202305047068 · Inner Sunset
3-story rear horizontal addition. excavate lower 1st floor slab on grade. convert partial garage to living space. (n) interior 1st to 2nd flr stair. (n) green & solar ready roofs. (n) fixtures & finishes. expand hydronic radiant heating. relocate utility meters. repave downsloping driveway.
- Filed
- May 4, 2023
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 26 stops across 4 departments
- Comments issued
- 4 times, by Building Inspection, Planning, Public Works
- Put on hold
- Once
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 4, 2023 | May 16, 2023 | — |
Zoning review Planning · CP-ZOC | May 16, 2023 | Oct 31, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | May 16, 2023 | In progress | Administrative |
Planning neighborhood notice Planning · CP-NP | Sep 6, 2023 | Sep 11, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Nov 1, 2023 | Dec 5, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Nov 1, 2023 | Nov 6, 2023 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Nov 1, 2023 | Nov 30, 2023 | Approved |
Structural plan approval Building Inspection · PAD-STR | Nov 29, 2023 | Jan 25, 2024 | Approved |
Building plan review Building Inspection · BLDG | Dec 26, 2023 | Jan 9, 2024 | Approved |
Zoning review Planning · CP-ZOC | Dec 26, 2023 | Jan 4, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Dec 26, 2023 | Jan 14, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Dec 26, 2023 | Jan 12, 2024 | Approved |
Zoning review Planning · CP-ZOC | May 2, 2024 | May 15, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | May 2, 2024 | May 10, 2024 | Approved-Stipulated |
Building plan review Building Inspection · BLDG | May 2, 2024 | May 3, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | May 2, 2024 | May 9, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 2, 2024 | May 10, 2024 | Approved |
Zoning review Planning · CP-ZOC | May 16, 2024 | May 29, 2024 | Approved |
Building plan review Building Inspection · BLDG | May 16, 2024 | May 21, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | May 16, 2024 | May 21, 2024 | Administrative |
Street use and mapping Public Works · DPW-BSM | May 16, 2024 | May 20, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | May 16, 2024 | May 23, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 13, 2025 | Jan 13, 2025 | Approved-Stipulated |
Structural plan approval Building Inspection · PAD-STR | Jan 13, 2025 | Jan 15, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 15, 2025 | In progress | — |
Development fee collection Building Inspection · DFCU | Jan 16, 2026 | Jan 16, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Approved
- Estimated cost
- $442,659
| Name | Role | License on permit |
|---|---|---|
| Dennis C Budd Dennis Budd Aia Architect | Architect | C26969 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2022