420 23rd St
San Francisco permit 202305057239 · Potrero Hill
Unit 3 bldg - mayoral ed 17-02. removal (e) steel boiler unit, and all associated non-structral equipment. a condenser unit, three intake pumps cooking water heat exchanger per ab-017
- Filed
- May 5, 2023
- Issued
- Jun 12, 2023 (1 month after filing)
- Completed
- May 28, 2024 (12 months after issuance)
- Review stops
- 6 stops across 4 departments
- Comments issued
- Not recorded for this permit
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | May 5, 2023 | May 5, 2023 | — |
Building plan review Building Inspection · BLDG | May 30, 2023 | May 30, 2023 | — |
Fire prevention review Fire Department · SFFD | May 31, 2023 | May 31, 2023 | — |
Zoning review Planning · CP-ZOC | Jun 8, 2023 | Jun 8, 2023 | — |
Public health review Public Health · HEALTH | Jun 12, 2023 | Jun 12, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Jun 12, 2023 | Jun 12, 2023 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $600,000
| Name | Role | License on permit |
|---|---|---|
| Paul Anthony Littler Holmes Structural | Engineer | S6189 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026