421 Leavenworth St #0
San Francisco permit 202305057244 · Tenderloin
Priority processing-100% affordable. 47 units+community room+offices. fire restoration & voluntary seismic. grd flr reconfiguration. in-kind stair repair/replacement. window repair/replace, door replace, (n) mep,hvac,exhaust,fixtures,appliances,mobility+communication units. historic facade remain.
- Filed
- May 5, 2023
- Issued
- Feb 19, 2025 (22 months after filing)
- Completed
- Nov 3, 2026 (20 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 46 stops across 6 departments
- Comments issued
- 21 times, by Building Inspection, Fire Department, Public Works, Public Health
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Apartment and hotel inspection Building Inspection · HIS | May 5, 2023 | May 5, 2023 | — |
Central Permit Bureau Building Inspection · CPB | May 5, 2023 | May 10, 2023 | — |
Zoning review Planning · CP-ZOC | May 10, 2023 | Jul 25, 2023 | — |
Permit Processing Center Building Inspection · PPC | May 10, 2023 | Apr 1, 2024 | — |
Building plan review Building Inspection · BLDG | Jul 26, 2023 | Aug 7, 2023 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jul 26, 2023 | Aug 23, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jul 26, 2023 | Aug 23, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jul 26, 2023 | Aug 28, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jul 26, 2023 | Aug 3, 2023 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Jul 26, 2023 | Aug 14, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 31, 2023 | Aug 31, 2023 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Sep 6, 2023 | Sep 14, 2023 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Oct 3, 2023 | Oct 3, 2023 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Nov 1, 2023 | Nov 1, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Nov 1, 2023 | Nov 13, 2023 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Nov 2, 2023 | Nov 2, 2023 | Approved |
Electrical plan review Building Inspection · MECH-E | Nov 7, 2023 | Nov 7, 2023 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Nov 7, 2023 | Nov 7, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Nov 9, 2023 | Nov 9, 2023 | Issued Comments |
Public Health HEALTH-MH | Nov 22, 2023 | Mar 12, 2024 | Approved-Stipulated |
Electrical plan review Building Inspection · MECH-E | Dec 19, 2023 | Dec 19, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Dec 20, 2023 | Dec 22, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Dec 20, 2023 | Dec 20, 2023 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Dec 20, 2023 | Dec 20, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Dec 21, 2023 | Dec 21, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jan 18, 2024 | Jan 22, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jan 19, 2024 | Jan 19, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Jan 19, 2024 | Jan 19, 2024 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Jan 19, 2024 | Jan 19, 2024 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Jan 22, 2024 | Jan 22, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Jan 22, 2024 | Jan 22, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jan 22, 2024 | Jan 22, 2024 | Approved |
Zoning review Planning · CP-ZOC | Jan 22, 2024 | Jan 23, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jan 22, 2024 | Jan 25, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 22, 2024 | Jan 24, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jan 22, 2024 | Jan 25, 2024 | Approved |
Public Health HEALTH-MH | Jan 31, 2024 | Jan 31, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Mar 5, 2024 | Mar 5, 2024 | Approved |
Zoning review Planning · CP-ZOC | Mar 18, 2024 | Mar 18, 2024 | Approved |
Building plan review Building Inspection · BLDG | Mar 18, 2024 | Mar 18, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Mar 18, 2024 | Mar 19, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Mar 18, 2024 | Mar 18, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Mar 18, 2024 | Mar 26, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 18, 2024 | Mar 26, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Mar 18, 2024 | Mar 29, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 1, 2024 | Feb 19, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $10,000,000
| Name | Role | License on permit |
|---|---|---|
| Pamela Anne Collier Levy Design Partners | Architect | C14940 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2025