San Francisco permit 202305057244 · Tenderloin

Home remodel (type unconfirmed)Full plan reviewComplete
Street view · Jan 2025
Google Street View of 421 Leavenworth St #0, Jan 2025
Scope of work
As written on the permit application.

Priority processing-100% affordable. 47 units+community room+offices. fire restoration & voluntary seismic. grd flr reconfiguration. in-kind stair repair/replacement. window repair/replace, door replace, (n) mep,hvac,exhaust,fixtures,appliances,mobility+communication units. historic facade remain.

Timeline
Key dates from the city record.
Filed
May 5, 2023
Issued
Feb 19, 2025 (22 months after filing)
Completed
Nov 3, 2026 (20 months after issuance)

For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
46 stops across 6 departments
Comments issued
21 times, by Building Inspection, Fire Department, Public Works, Public Health
Review stopFinishedResult

Apartment and hotel inspection

Building Inspection · HIS

May 5, 2023—

Central Permit Bureau

Building Inspection · CPB

May 10, 2023—

Zoning review

Planning · CP-ZOC

Jul 25, 2023—

Permit Processing Center

Building Inspection · PPC

Apr 1, 2024—

Building plan review

Building Inspection · BLDG

Aug 7, 2023Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Aug 23, 2023Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Aug 23, 2023Issued Comments

Fire prevention review

Fire Department · SFFD

Aug 28, 2023Issued Comments

Street use and mapping

Public Works · DPW-BSM

Aug 3, 2023Approved-Stipulated

Public Utilities Commission review

Public Utilities · SFPUC

Aug 14, 2023Approved

Mechanical and energy plan review

Building Inspection · MECH

Aug 31, 2023Issued Comments

Electrical plan review

Building Inspection · MECH-E

Sep 14, 2023Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Oct 3, 2023Administrative

Mechanical and energy plan review

Building Inspection · MECH

Nov 1, 2023Issued Comments

Fire prevention review

Fire Department · SFFD

Nov 13, 2023Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Nov 2, 2023Approved

Electrical plan review

Building Inspection · MECH-E

Nov 7, 2023Issued Comments

Electrical plan review

Building Inspection · MECH-E

Nov 7, 2023Issued Comments

Building plan review

Building Inspection · BLDG

Nov 9, 2023Issued Comments

Public Health

HEALTH-MH

Mar 12, 2024Approved-Stipulated

Electrical plan review

Building Inspection · MECH-E

Dec 19, 2023Issued Comments

Building plan review

Building Inspection · BLDG

Dec 22, 2023Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Dec 20, 2023Issued Comments

Electrical plan review

Building Inspection · MECH-E

Dec 20, 2023Issued Comments

Fire prevention review

Fire Department · SFFD

Dec 21, 2023Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Jan 22, 2024Approved

Building plan review

Building Inspection · BLDG

Jan 19, 2024Approved

Electrical plan review

Building Inspection · MECH-E

Jan 19, 2024Issued Comments

Electrical plan review

Building Inspection · MECH-E

Jan 19, 2024Issued Comments

Electrical plan review

Building Inspection · MECH-E

Jan 22, 2024Approved

Fire prevention review

Fire Department · SFFD

Jan 22, 2024Issued Comments

Fire prevention review

Fire Department · SFFD

Jan 22, 2024Approved

Zoning review

Planning · CP-ZOC

Jan 23, 2024Approved

Structural plan approval

Building Inspection · PAD-STR

Jan 25, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Jan 24, 2024Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Jan 25, 2024Approved

Public Health

HEALTH-MH

Jan 31, 2024Issued Comments

Street use and mapping

Public Works · DPW-BSM

Mar 5, 2024Approved

Zoning review

Planning · CP-ZOC

Mar 18, 2024Approved

Building plan review

Building Inspection · BLDG

Mar 18, 2024Approved

Structural plan approval

Building Inspection · PAD-STR

Mar 19, 2024Approved

Electrical plan review

Building Inspection · MECH-E

Mar 18, 2024Approved

Fire prevention review

Fire Department · SFFD

Mar 26, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Mar 26, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

Mar 29, 2024Approved

Central Permit Bureau

Building Inspection · CPB

Feb 19, 2025Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$10,000,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Pamela Anne Collier

Levy Design Partners

ArchitectC14940
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202305057244 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record