261 Texas St
San Francisco permit 202305087288 · Potrero Hill
Add spiral stairs to 2/f deck, connect to landing area of (e) 1/f deck landing area
- Filed
- May 8, 2023
- Issued
- Oct 7, 2024 (17 months after filing)
- Completed
- Apr 4, 2025 (6 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 17 stops across 3 departments
- Comments issued
- 3 times, by Planning, Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | May 8, 2023 | May 8, 2023 | — |
Zoning review Planning · CP-ZOC | May 8, 2023 | Aug 4, 2023 | Issued Comments |
Central Permit Bureau Building Inspection · CPB | Jun 28, 2023 | Jun 28, 2023 | — |
Planning neighborhood notice Planning · CP-NP | Oct 3, 2023 | Oct 10, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Jan 18, 2024 | Jan 18, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jan 22, 2024 | Feb 7, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Feb 7, 2024 | Feb 9, 2024 | Approved |
Building plan review Building Inspection · BLDG | Mar 11, 2024 | Mar 11, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Jun 21, 2024 | Jun 21, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Aug 6, 2024 | Aug 6, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 6, 2024 | Aug 9, 2024 | Approved |
Zoning review Planning · CP-ZOC | Aug 12, 2024 | Aug 20, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Aug 20, 2024 | Oct 1, 2024 | Administrative |
Street use and mapping Public Works · DPW-BSM | Sep 3, 2024 | Sep 5, 2024 | Approved |
Zoning review Planning · CP-ZOC | Sep 6, 2024 | Sep 25, 2024 | Approved |
Building plan review Building Inspection · BLDG | Sep 25, 2024 | Oct 1, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 1, 2024 | Oct 7, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $15,000
| Name | Role | License on permit |
|---|---|---|
| Venkata Rohit Grandhi | Engineer | C-88709 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2025