447 Clipper St
San Francisco permit 202305117567 · Noe Valley
New subterranean garage. no increase to habitable area.
- Filed
- May 11, 2023
- Issued
- Feb 25, 2025 (22 months after filing)
- Completed
- Apr 21, 2026 (14 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 18 stops across 3 departments
- Comments issued
- 5 times, by Building Inspection, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 11, 2023 | May 12, 2023 | — |
Zoning review Planning · CP-ZOC | May 12, 2023 | Nov 29, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | May 12, 2023 | Feb 25, 2025 | Administrative |
Planning neighborhood notice Planning · CP-NP | Oct 2, 2023 | Oct 5, 2023 | Approved |
Building plan review Building Inspection · BLDG | Dec 7, 2023 | Feb 2, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Dec 7, 2023 | Jan 30, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Dec 7, 2023 | Dec 11, 2023 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Dec 11, 2023 | Jan 2, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jan 30, 2024 | Jan 30, 2024 | Approved |
Urban forestry Public Works · DPW-BUF | May 28, 2024 | May 28, 2024 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Jul 26, 2024 | Jul 26, 2024 | Approved |
Building plan review Building Inspection · BLDG | Oct 8, 2024 | Oct 17, 2024 | Approved |
Zoning review Planning · CP-ZOC | Oct 8, 2024 | Jan 13, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 8, 2024 | Oct 15, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Oct 8, 2024 | Oct 17, 2024 | Approved |
Urban forestry Public Works · DPW-BUF | Oct 8, 2024 | Oct 11, 2024 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Dec 23, 2024 | Dec 23, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 25, 2025 | Feb 25, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $95,000
| Name | Role | License on permit |
|---|---|---|
| Mason Robert Kirby Mason Kirby Inc. | Architect | C-29468 |
| Donald David Double D Engineering | Engineer | S3928 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2019