San Francisco permit 202305117579 · Mission

ADUFull plan reviewIssued
Street view · Jan 2018
Google Street View of 65 Oakwood St, Jan 2018
Scope of work
As written on the permit application.

Add (2) adu to ground floor per ord 162-16 in areas currently used as garage and unused storage. soft story retrofit under separate permit.

Timeline
Key dates from the city record.
Filed
May 11, 2023
Issued
Oct 7, 2024 (17 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
29 stops across 5 departments
Comments issued
6 times, by Planning, Building Inspection
Put on hold
Once
Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

May 18, 2023—

Zoning review

Planning · CP-ZOC

Sep 1, 2023Issued Comments

Building plan review

Building Inspection · BLDG

Jun 22, 2023Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Apr 5, 2024—

Fire prevention review

Fire Department · SFFD

May 24, 2023—

Street use and mapping

Public Works · DPW-BSM

May 22, 2023Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jun 1, 2023—

Zoning review

Planning · CP-ZOC

Apr 17, 2024Issued Comments

Building plan review

Building Inspection · BLDG

Apr 18, 2024Administrative

Building plan review

Building Inspection · BLDG

Apr 23, 2024Issued Comments

Fire prevention review

Fire Department · SFFD

Mar 26, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Apr 1, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Mar 26, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

Apr 5, 2024Issued Comments

Zoning review

Planning · CP-ZOC

Jul 18, 2024Approved

Building plan review

Building Inspection · BLDG

Jun 10, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Jun 4, 2024Approved

Fire prevention review

Fire Department · SFFD

Jun 4, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Jun 5, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jun 4, 2024Approved

Building plan review

Building Inspection · BLDG

Jun 18, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

Jun 21, 2024Approved

Fire prevention review

Fire Department · SFFD

Jun 17, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Jun 18, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jun 20, 2024Approved

Zoning review

Planning · CP-ZOC

Sep 26, 2024Approved

Development fee collection

Building Inspection · DFCU

Sep 20, 2024Administrative

Permit Processing Center

Building Inspection · PPC

Sep 20, 2024Administrative

Central Permit Bureau

Building Inspection · CPB

Oct 7, 2024Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$400,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Gary Wayne Meyer

Wayne Myer Works Arch

ArchitectC31705
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202305117579 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record