San Francisco permit 202305127657 · Tenderloin

Revision or supplementOver-the-counter, with plansComplete

This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.

Street view · May 2025
Google Street View of 335 Powell St, May 2025
Scope of work
As written on the permit application.

Proposed renovation of existing retail space along geary blvd. fire sprinkler and fire alarm-deferred submittal

Timeline
Key dates from the city record.
Filed
May 12, 2023
Issued
Jun 21, 2024 (13 months after filing)
Completed
Jun 5, 2025 (11 months after issuance)
City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
22 stops across 6 departments
Comments issued
3 times, by Fire Department, Public Health, Public Works
Review stopFinishedResult

Code enforcement

Building Inspection · CES

May 12, 2023—

Intake

Building Inspection · INTAKE

May 12, 2023—

Zoning review

Planning · CP-ZOC

May 12, 2023—

Zoning review

Planning · CP-ZOC

Jun 28, 2023—

Mechanical and energy plan review

Building Inspection · MECH

Jun 28, 2023—

Electrical plan review

Building Inspection · MECH-E

Jun 28, 2023—

Zoning review

Planning · CP-ZOC

Jul 18, 2023—

Mechanical and energy plan review

Building Inspection · MECH

Jul 18, 2023—

Electrical plan review

Building Inspection · MECH-E

Jul 18, 2023—

Zoning review

Planning · CP-ZOC

Sep 13, 2023Approved

Building plan review

Building Inspection · BLDG

Sep 13, 2023Approved

Structural plan approval

Building Inspection · PAD-STR

Sep 13, 2023Approved

Fire prevention review

Fire Department · SFFD

Sep 13, 2023Issued Comments

Fire prevention review

Fire Department · SFFD

Sep 15, 2023Approved

Public health review

Public Health · HEALTH

Sep 15, 2023Administrative

Public health review

Public Health · HEALTH

Sep 25, 2023Issued Comments

Public health review

Public Health · HEALTH

Sep 27, 2023Approved

Street use and mapping

Public Works · DPW-BSM

Sep 29, 2023Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Sep 29, 2023Approved

Zoning review

Planning · CP-ZOC

Oct 10, 2023Approved

Street use and mapping

Public Works · DPW-BSM

Mar 1, 2024Approved

Central Permit Bureau

Building Inspection · CPB

Jun 21, 2024Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
OTC alterations permit
Status
Complete
Estimated cost
$373,650
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Michael John Stanton

Stanton Architecture

ArchitectC11562
Steven F Lew

Tuan & Robinson S.E. Inc.

EngineerS4180
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202305127657 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record