1220 Treat Av
San Francisco permit 202305167860 · Mission
Convert unimproved space at g/l into living space included living rm w/ kitchenette, bedrooms, bathrooms, laundry rm, and new interior stair connecting to main fl above. (net new sf: 1280 sf)
- Filed
- May 16, 2023
- Issued
- Jan 9, 2024 (8 months after filing)
- Completed
- Mar 3, 2026 (26 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 17 stops across 5 departments
- Comments issued
- 3 times, by Building Inspection, Public Works, Public Utilities
- Put on hold
- Once
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | May 16, 2023 | May 16, 2023 | — |
Zoning review Planning · CP-ZOC | May 16, 2023 | May 16, 2023 | — |
Permit Center Permit Center · PERMIT-CTR | May 16, 2023 | May 16, 2023 | — |
Central Permit Bureau Building Inspection · CPB | May 22, 2023 | Jun 1, 2023 | — |
Building pre-screening Building Inspection · PRE-BLDG | May 22, 2023 | May 22, 2023 | — |
Building plan review Building Inspection · BLDG | Jun 1, 2023 | Oct 26, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 7, 2023 | Sep 22, 2023 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Sep 22, 2023 | Sep 26, 2023 | Administrative |
Street use and mapping Public Works · DPW-BSM | Sep 26, 2023 | Sep 28, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Sep 29, 2023 | Oct 13, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Oct 19, 2023 | Nov 7, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 19, 2023 | Oct 19, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 11, 2023 | Dec 11, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 12, 2023 | Dec 14, 2023 | Approved |
Zoning review Planning · CP-ZOC | Dec 14, 2023 | Dec 19, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Dec 20, 2023 | Dec 20, 2023 | Administrative |
Central Permit Bureau Building Inspection · CPB | Dec 20, 2023 | Jan 9, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $312,550
| Name | Role | License on permit |
|---|---|---|
| Andrew Yongsupp Lee Andrew Lee Architecture | Architect | C29239 |
| Zachary Lee Westling Wmengineering | Engineer | s6781 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026