290 Turk St
San Francisco permit 202305167895 · Tenderloin
T.i. in basement (file storage). no structural work. no change to path of travel. total area to be renovated of 524sf.
- Filed
- May 16, 2023
- Issued
- Apr 3, 2024 (11 months after filing)
- Completed
- Mar 21, 2025 (12 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2023 were typically issued within 1 month (median of 4,704 issued permits).
- Review stops
- 8 stops across 2 departments
- Comments issued
- None
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | May 16, 2023 | May 16, 2023 | — |
Zoning review Planning · CP-ZOC | May 16, 2023 | May 16, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | May 16, 2023 | May 16, 2023 | — |
Intake Building Inspection · INTAKE | May 31, 2023 | May 31, 2023 | — |
Intake Building Inspection · INTAKE | Jun 6, 2023 | Jun 6, 2023 | — |
Building plan review Building Inspection · BLDG | Jun 6, 2023 | Jun 6, 2023 | — |
Electrical plan review Building Inspection · MECH-E | Jun 6, 2023 | Jun 6, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Apr 3, 2024 | Apr 3, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $105,000
| Name | Role | License on permit |
|---|---|---|
| Samuel Nelson Karioki Mathau Mathau/ Roche Design Group | Authorized agent-others | C 21576 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2025