91 Coleridge St

San Francisco permit 202305177937 · Bernal Heights

AdditionFull plan reviewIssued
Street view · Jul 2015
Google Street View of 91 Coleridge St, Jul 2015
Scope of work
As written on the permit application.

Front & rear yard addition. rear yard variance. 1st: (n) porch @ front. 2nd: (n) addition @ m.bath to align w/ floor below. renovation of 2 baths, (n) hallway to rear yard. roof: (n) skylight. (n) ext. stairs @ front of building

Timeline
Key dates from the city record.
Filed
May 17, 2023
Issued
Jan 7, 2025 (20 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
29 stops across 6 departments
Comments issued
4 times, by Building Inspection, Public Works
Put on hold
Once

Main permit

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

May 23, 2023—

Zoning review

Planning · CP-ZOC

Oct 25, 2023Approved

Permit Processing Center

Building Inspection · PPC

Dec 19, 2024Administrative

Planning neighborhood notice

Planning · CP-NP

Aug 3, 2023Approved

Building plan review

Building Inspection · BLDG

Nov 29, 2023Issued Comments

Street use and mapping

Public Works · DPW-BSM

Nov 13, 2023Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Nov 30, 2023Approved

Structural plan approval

Building Inspection · PAD-STR

Feb 6, 2024Approved

Building plan review

Building Inspection · BLDG

Nov 27, 2024Approved

Zoning review

Planning · CP-ZOC

Nov 26, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Nov 27, 2024Approved

Structural plan approval

Building Inspection · PAD-STR

Dec 9, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Dec 16, 2024Approved

Central Permit Bureau

Building Inspection · CPB

Jan 7, 2025Administrative

Addendum 1: Foundation,structural,t-24,final plans

Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Feb 13, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Feb 18, 2025Administrative

Zoning review

Planning · CP-ZOC

May 28, 2025Approved

Building plan review

Building Inspection · BLDG

Mar 11, 2025Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Apr 8, 2025Approved

Fire prevention review

Fire Department · SFFD

Mar 11, 2025Not Applicable

Street use and mapping

Public Works · DPW-BSM

Feb 19, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Feb 26, 2025Approved

Permit Processing Center

Building Inspection · PPC

Jun 3, 2025Administrative

Building plan review

Building Inspection · BLDG

Apr 25, 2025Issued Comments

Building plan review

Building Inspection · BLDG

May 23, 2025Approved

Street use and mapping

Public Works · DPW-BSM

May 30, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

May 30, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Jun 3, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Jul 10, 2025Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$75,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Sven Erik Lavine

Sven Lavine Architecture

ArchitectC30122
Sean Thomas Condry

Stc Design & Engineering

EngineerC60860
Sources