91 Coleridge St
San Francisco permit 202305177937 · Bernal Heights
Front & rear yard addition. rear yard variance. 1st: (n) porch @ front. 2nd: (n) addition @ m.bath to align w/ floor below. renovation of 2 baths, (n) hallway to rear yard. roof: (n) skylight. (n) ext. stairs @ front of building
- Filed
- May 17, 2023
- Issued
- Jan 7, 2025 (20 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 29 stops across 6 departments
- Comments issued
- 4 times, by Building Inspection, Public Works
- Put on hold
- Once
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 17, 2023 | May 23, 2023 | — |
Zoning review Planning · CP-ZOC | May 23, 2023 | Oct 25, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | May 23, 2023 | Dec 19, 2024 | Administrative |
Planning neighborhood notice Planning · CP-NP | Jul 26, 2023 | Aug 3, 2023 | Approved |
Building plan review Building Inspection · BLDG | Oct 26, 2023 | Nov 29, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Oct 26, 2023 | Nov 13, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Oct 26, 2023 | Nov 30, 2023 | Approved |
Structural plan approval Building Inspection · PAD-STR | Nov 28, 2023 | Feb 6, 2024 | Approved |
Building plan review Building Inspection · BLDG | Nov 12, 2024 | Nov 27, 2024 | Approved |
Zoning review Planning · CP-ZOC | Nov 26, 2024 | Nov 26, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 27, 2024 | Nov 27, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Dec 2, 2024 | Dec 9, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 2, 2024 | Dec 16, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 19, 2024 | Jan 7, 2025 | Administrative |
Addendum 1: Foundation,structural,t-24,final plans
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jan 27, 2025 | Feb 13, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 14, 2025 | Feb 18, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Feb 18, 2025 | May 28, 2025 | Approved |
Building plan review Building Inspection · BLDG | Feb 18, 2025 | Mar 11, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Feb 18, 2025 | Apr 8, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Feb 18, 2025 | Mar 11, 2025 | Not Applicable |
Street use and mapping Public Works · DPW-BSM | Feb 18, 2025 | Feb 19, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 18, 2025 | Feb 26, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Feb 18, 2025 | Jun 3, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Apr 24, 2025 | Apr 25, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | May 23, 2025 | May 23, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | May 28, 2025 | May 30, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 28, 2025 | May 30, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 30, 2025 | Jun 3, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 3, 2025 | Jul 10, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $75,000
| Name | Role | License on permit |
|---|---|---|
| Sven Erik Lavine Sven Lavine Architecture | Architect | C30122 |
| Sean Thomas Condry Stc Design & Engineering | Engineer | C60860 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jul 2015