450 39th Av
San Francisco permit 202305198149 · Outer Richmond
Remodel 1st fl and add 439sf to 1st fl only at rear of property for two bedrmm 1000sf adu. no change to front facade. no change to building height. (new rear roof deck, spiral stairs, 2nd fl rear door, 2nd fl laundry room to be under separate permit).
- Filed
- May 19, 2023
- Issued
- Jul 30, 2024 (14 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 34 stops across 5 departments
- Comments issued
- 11 times, by Planning, Building Inspection, Public Works
- Put on hold
- Twice
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 19, 2023 | Jun 2, 2023 | — |
Zoning review Planning · CP-ZOC | Jun 2, 2023 | Aug 11, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Jun 2, 2023 | Apr 1, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jun 2, 2023 | Sep 13, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jun 2, 2023 | Jun 13, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jun 2, 2023 | Jun 8, 2023 | — |
Urban forestry Public Works · DPW-BUF | Jun 2, 2023 | Sep 12, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Jun 2, 2023 | Jul 15, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Aug 28, 2023 | Aug 29, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Aug 28, 2023 | Sep 6, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 28, 2023 | Sep 12, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Aug 28, 2023 | Aug 29, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 28, 2023 | Aug 31, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 20, 2024 | Feb 20, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Mar 22, 2024 | Mar 28, 2024 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Mar 22, 2024 | Apr 8, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Mar 22, 2024 | Apr 29, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 22, 2024 | Mar 26, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 9, 2024 | Apr 9, 2024 | Approved |
Building plan review Building Inspection · BLDG | Apr 15, 2024 | Apr 18, 2024 | Issued Comments |
Building plan review quality control Building Inspection · BLDG-QC | Apr 30, 2024 | Apr 30, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Jun 3, 2024 | Jun 3, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jun 3, 2024 | Jul 1, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jun 3, 2024 | Jun 3, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jun 4, 2024 | Jun 4, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jun 12, 2024 | Jun 12, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Jun 27, 2024 | Jun 27, 2024 | Approved |
Zoning review Planning · CP-ZOC | Jun 28, 2024 | Jul 11, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jun 28, 2024 | Jun 28, 2024 | Approved |
Urban forestry Public Works · DPW-BUF | Jun 28, 2024 | Jul 11, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jun 28, 2024 | Jul 2, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 28, 2024 | Jul 2, 2024 | Approved |
Development fee collection Building Inspection · DFCU | Jul 12, 2024 | Jul 15, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | Jul 15, 2024 | Jul 30, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $280,000
| Name | Role | License on permit |
|---|---|---|
| Michael Allen Goeringer | Architect | C31971 |
| Amarendra Prasad Design Everst, Inc | Engineer | C68517 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2019