2636 San Bruno Av
San Francisco permit 202305198166 · Portola
Change of use: establish a full-service restaurant a-2 from brewery/tasting room.
- Filed
- May 19, 2023
- Issued
- Aug 29, 2023 (3 months after filing)
- Completed
- Mar 29, 2024 (7 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 18 stops across 6 departments
- Comments issued
- None
- Put on hold
- Once
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | May 19, 2023 | May 19, 2023 | — |
Zoning review Planning · CP-ZOC | May 19, 2023 | May 19, 2023 | — |
Building plan review Building Inspection · BLDG | May 19, 2023 | May 19, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | May 19, 2023 | May 19, 2023 | — |
Fire prevention review Fire Department · SFFD | May 19, 2023 | May 19, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | May 19, 2023 | May 19, 2023 | — |
Public health review Public Health · HEALTH | May 19, 2023 | May 19, 2023 | — |
Central Permit Bureau Building Inspection · CPB | May 22, 2023 | May 22, 2023 | — |
Fire prevention review Fire Department · SFFD | May 22, 2023 | Aug 3, 2023 | Approved-Stipulated |
Permit Center Permit Center · PERMIT-CTR | May 22, 2023 | May 22, 2023 | — |
Building plan review Building Inspection · BLDG | Aug 4, 2023 | Aug 7, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Aug 7, 2023 | Aug 16, 2023 | Approved-Stipulated |
Mechanical and energy plan review Building Inspection · MECH | Aug 16, 2023 | Aug 17, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 17, 2023 | Aug 21, 2023 | Approved |
Zoning review Planning · CP-ZOC | Aug 21, 2023 | Aug 23, 2023 | Approved |
Public health review Public Health · HEALTH | Aug 24, 2023 | Aug 24, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Aug 24, 2023 | Aug 25, 2023 | Administrative |
Central Permit Bureau Building Inspection · CPB | Aug 25, 2023 | Aug 29, 2023 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $5,000
| Name | Role | License on permit |
|---|---|---|
| Charles Gatton Hemminger Charles Hemminger Associates | Architect | C-24965 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025