275 South Van Ness Av
San Francisco permit 202305198219 · Mission
Change of occupancy: ti to existing building to establish distillery with accessory tasting room and cafe. associated bp#s:2022-1222-9044, 2022-1222-9047, 2023-0414-5798 and 2023-0414-5800. certificate of occupancy for this permit only after associated permits receive certificate of occupancy.
- Filed
- May 31, 2023
- Issued
- May 21, 2024 (12 months after filing)
- Completed
- Feb 25, 2025 (9 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 45 stops across 6 departments
- Comments issued
- 11 times, by Building Inspection, Fire Department
- Put on hold
- Once
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Building pre-screening Building Inspection · PRE-BLDG | May 19, 2023 | May 22, 2023 | — |
Central Permit Bureau Building Inspection · CPB | May 23, 2023 | May 31, 2023 | — |
Zoning review Planning · CP-ZOC | May 31, 2023 | Jun 1, 2023 | — |
Permit Processing Center Building Inspection · PPC | May 31, 2023 | May 15, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Jun 1, 2023 | Aug 15, 2023 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jun 1, 2023 | Nov 6, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jun 1, 2023 | Jul 27, 2023 | — |
Fire prevention review Fire Department · SFFD | Jun 1, 2023 | Jul 6, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jun 1, 2023 | Jun 21, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jun 1, 2023 | Jun 27, 2023 | — |
Public health review Public Health · HEALTH | Jun 1, 2023 | Jul 6, 2023 | — |
Public Health HEALTH-HM | Jun 1, 2023 | Jun 9, 2023 | — |
Public health food review Public Health · HEALTH-FD | Jun 1, 2023 | Jun 13, 2023 | — |
Public health food review Public Health · HEALTH-FD | Jul 6, 2023 | Jul 6, 2023 | — |
Electrical plan review Building Inspection · MECH-E | Jul 24, 2023 | Aug 15, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jul 27, 2023 | Jul 27, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Oct 5, 2023 | Oct 20, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Oct 12, 2023 | Oct 13, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Nov 2, 2023 | Nov 16, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Dec 18, 2023 | Dec 28, 2023 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Dec 26, 2023 | Feb 16, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jan 12, 2024 | Jan 29, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Feb 12, 2024 | Feb 26, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Mar 4, 2024 | Mar 6, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Mar 6, 2024 | Mar 6, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Mar 18, 2024 | Mar 18, 2024 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Mar 25, 2024 | Mar 25, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Mar 25, 2024 | Mar 25, 2024 | Approved |
Zoning review Planning · CP-ZOC | Mar 25, 2024 | Mar 26, 2024 | Approved |
Building plan review Building Inspection · BLDG | Mar 25, 2024 | Apr 5, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Mar 25, 2024 | Apr 19, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Mar 25, 2024 | May 2, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 25, 2024 | Apr 1, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 25, 2024 | Mar 29, 2024 | Approved |
Public health food review Public Health · HEALTH-FD | Mar 25, 2024 | Apr 9, 2024 | Approved |
Public health review Public Health · HEALTH | Mar 25, 2024 | Mar 26, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 19, 2024 | Apr 19, 2024 | Approved |
Building plan review Building Inspection · BLDG | Apr 19, 2024 | Apr 25, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Apr 22, 2024 | Apr 22, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | May 3, 2024 | May 13, 2024 | Approved |
Public health review Public Health · HEALTH | May 3, 2024 | May 7, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 3, 2024 | May 6, 2024 | Approved |
Public health food review Public Health · HEALTH-FD | May 3, 2024 | May 6, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | May 14, 2024 | May 21, 2024 | Administrative |
Development fee collection Building Inspection · DFCU | May 15, 2024 | May 15, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $447,819
| Name | Role | License on permit |
|---|---|---|
| Bonnie Louise Bridges Studio Bba | Architect | C23785 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026