1068 Florida St
San Francisco permit 202305228274 · Mission
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
Altered site permit: to #202101152820 pursuant to fourplex legislation/density exceptions. construct new 4 unit multi-family residential building with two-car common use garage
- Filed
- May 22, 2023
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 51 stops across 5 departments
- Comments issued
- 13 times, by Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 22, 2023 | Jun 2, 2023 | — |
Zoning review Planning · CP-ZOC | Jun 2, 2023 | Jan 24, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Jun 2, 2023 | Jul 24, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Jan 25, 2024 | Feb 7, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jan 25, 2024 | Feb 27, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jan 25, 2024 | Jan 30, 2024 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | Jan 25, 2024 | Feb 29, 2024 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Jan 25, 2024 | Jan 26, 2024 | Approved |
Building plan review Building Inspection · BLDG | Feb 8, 2024 | Feb 8, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Jun 4, 2024 | Jun 5, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jun 5, 2024 | Jun 5, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Jun 6, 2024 | Jun 6, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Oct 2, 2024 | Oct 15, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Oct 3, 2024 | Dec 9, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Oct 3, 2024 | Oct 11, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Oct 3, 2024 | Oct 8, 2024 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | Oct 3, 2024 | Nov 23, 2024 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Oct 3, 2024 | Oct 4, 2024 | Approved |
Zoning review Planning · CP-ZOC | Mar 19, 2025 | Apr 22, 2025 | Approved |
Building plan review Building Inspection · BLDG | Mar 19, 2025 | Mar 20, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Mar 19, 2025 | Mar 26, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Mar 19, 2025 | Mar 20, 2025 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | Mar 19, 2025 | Apr 22, 2025 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Mar 19, 2025 | Mar 21, 2025 | Approved |
Zoning review Planning · CP-ZOC | Aug 18, 2025 | Oct 1, 2025 | Approved |
Building plan review Building Inspection · BLDG | Aug 18, 2025 | Aug 25, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Aug 18, 2025 | May 15, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Aug 18, 2025 | Aug 26, 2025 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | Aug 18, 2025 | Aug 29, 2025 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Aug 18, 2025 | Sep 2, 2025 | Approved |
Zoning review Planning · CP-ZOC | Nov 21, 2025 | Apr 24, 2026 | Approved |
Building plan review Building Inspection · BLDG | Nov 21, 2025 | Nov 26, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Nov 21, 2025 | Nov 24, 2025 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | Nov 21, 2025 | Dec 3, 2025 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Nov 21, 2025 | Nov 26, 2025 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Mar 16, 2026 | Mar 16, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Apr 24, 2026 | May 8, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Apr 24, 2026 | Apr 27, 2026 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | Apr 24, 2026 | Jun 5, 2026 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Apr 24, 2026 | Apr 28, 2026 | Approved |
Zoning review Planning · CP-ZOC | Apr 28, 2026 | Apr 30, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Apr 28, 2026 | Apr 30, 2026 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Apr 28, 2026 | May 1, 2026 | Approved |
Zoning review Planning · CP-ZOC | Jun 26, 2026 | Jul 14, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jun 26, 2026 | Jul 1, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jun 26, 2026 | Jul 6, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Jun 26, 2026 | Jul 1, 2026 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | Jun 26, 2026 | Jul 24, 2026 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Jun 26, 2026 | Jun 29, 2026 | Approved |
Development fee collection Building Inspection · DFCU | Jul 24, 2026 | Jul 24, 2026 | Administrative |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Filed
- Estimated cost
- $631,000
| Name | Role | License on permit |
|---|---|---|
| Gregory M Smith | Architect | C26697 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2025