1515 19th Av
San Francisco permit 202305228313 · Sunset/Parkside
Installing 3(n) antennas. installing 9(n) antenna mounts. relocating 6(e) antennas. removing 6(e) antenna mounts. r&r (e) frp screen w/(n) frp screen @sector b; (3)(e) rrus-32 b2 units w/3(n) radio 8843 units @antennas; (3)(e)rrus-32 b66a units w/3(n) radio 4449 units @antennas; 6(e) raycap 3315....
- Filed
- May 22, 2023
- Issued
- Feb 2, 2026 (32 months after filing)
- Completed
- Jun 5, 2026 (4 months after issuance)
- Review stops
- 19 stops across 4 departments
- Comments issued
- Twice, by Fire Department, Public Health
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 22, 2023 | Sep 29, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Sep 29, 2023 | Nov 2, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Sep 29, 2023 | Sep 26, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Nov 2, 2023 | Jan 2, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Nov 2, 2023 | Dec 15, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Nov 2, 2023 | Jan 29, 2024 | Issued Comments |
Public health review Public Health · HEALTH | Nov 2, 2023 | Nov 6, 2023 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Dec 14, 2023 | Dec 19, 2023 | Approved |
Zoning review Planning · CP-ZOC | Sep 9, 2025 | Sep 11, 2025 | Approved |
Building plan review Building Inspection · BLDG | Sep 9, 2025 | Sep 11, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 9, 2025 | Sep 25, 2025 | Approved |
Electrical plan review Building Inspection · MECH-E | Sep 9, 2025 | Sep 11, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Sep 9, 2025 | Sep 19, 2025 | Approved |
Public health review Public Health · HEALTH | Sep 9, 2025 | Sep 16, 2025 | Approved |
Zoning review Planning · CP-ZOC | Sep 19, 2025 | Sep 25, 2025 | Approved |
Building plan review Building Inspection · BLDG | Sep 19, 2025 | Sep 23, 2025 | Approved |
Electrical plan review Building Inspection · MECH-E | Sep 19, 2025 | Sep 22, 2025 | Approved |
Public health review Public Health · HEALTH | Sep 19, 2025 | Sep 25, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 26, 2025 | Feb 2, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $60,000
| Name | Role | License on permit |
|---|---|---|
| Jacob Scott Proctor Solar Communications | Engineer | C-70567 |
| James Spore | Engineer | S6336 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026