Scope of work
As written on the permit application.

Change of occupancy: ti to existing building to establish distillery with accessory tasting room and cafe. associated bp#s:2022-1222-9044, 2022-1222-9047, 2023-0414-5798 and 2023-0414-5800. certificate of occupancy for this permit only after certificate of occupancy for associated permits.

Timeline
Key dates from the city record.
Filed
May 23, 2023
Issued
May 21, 2024 (12 months after filing)
Completed
Feb 25, 2025 (9 months after issuance)

For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
49 stops across 6 departments
Comments issued
14 times, by Building Inspection, Fire Department
Put on hold
Once
Review stopFinishedResult

Building pre-screening

Building Inspection · PRE-BLDG

May 22, 2023—

Central Permit Bureau

Building Inspection · CPB

May 31, 2023—

Zoning review

Planning · CP-ZOC

Jun 1, 2023—

Permit Processing Center

Building Inspection · PPC

May 15, 2024Administrative

Building plan review

Building Inspection · BLDG

Aug 15, 2023Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Nov 6, 2023Approved

Mechanical and energy plan review

Building Inspection · MECH

Jul 27, 2023—

Fire prevention review

Fire Department · SFFD

Aug 31, 2023Issued Comments

Street use and mapping

Public Works · DPW-BSM

Jun 21, 2023—

Public Utilities Commission review

Public Utilities · SFPUC

Jun 27, 2023—

Public health review

Public Health · HEALTH

Jul 6, 2023—

Public Health

HEALTH-HM

Jun 9, 2023—

Public health food review

Public Health · HEALTH-FD

Jun 7, 2023—

Public health food review

Public Health · HEALTH-FD

Jul 6, 2023—

Electrical plan review

Building Inspection · MECH-E

Aug 9, 2023Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Jul 27, 2023Issued Comments

Building plan review

Building Inspection · BLDG

Oct 20, 2023Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Oct 13, 2023Issued Comments

Electrical plan review

Building Inspection · MECH-E

Oct 19, 2023Issued Comments

Building plan review

Building Inspection · BLDG

Nov 16, 2023Issued Comments

Building plan review

Building Inspection · BLDG

Dec 28, 2023Issued Comments

Building plan review

Building Inspection · BLDG

Jan 29, 2024Issued Comments

Building plan review

Building Inspection · BLDG

Feb 26, 2024Approved

Structural plan approval

Building Inspection · PAD-STR

Feb 16, 2024Approved

Electrical plan review

Building Inspection · MECH-E

Feb 27, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Mar 6, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Mar 18, 2024Issued Comments

Electrical plan review

Building Inspection · MECH-E

Mar 18, 2024Issued Comments

Fire prevention review

Fire Department · SFFD

Mar 18, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

Mar 25, 2024Approved

Electrical plan review

Building Inspection · MECH-E

Mar 25, 2024Approved

Zoning review

Planning · CP-ZOC

Mar 26, 2024Approved

Building plan review

Building Inspection · BLDG

Apr 5, 2024Approved

Structural plan approval

Building Inspection · PAD-STR

Apr 29, 2024Approved

Fire prevention review

Fire Department · SFFD

May 2, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Apr 1, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Mar 29, 2024Approved

Public health review

Public Health · HEALTH

Mar 26, 2024Approved

Public health food review

Public Health · HEALTH-FD

Apr 9, 2024Approved

Building plan review

Building Inspection · BLDG

Apr 5, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

Apr 19, 2024Approved

Building plan review

Building Inspection · BLDG

Apr 25, 2024Approved

Electrical plan review

Building Inspection · MECH-E

Apr 22, 2024Approved

Street use and mapping

Public Works · DPW-BSM

May 13, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

May 6, 2024Approved

Public health review

Public Health · HEALTH

May 7, 2024Approved

Public health food review

Public Health · HEALTH-FD

May 6, 2024Approved

Central Permit Bureau

Building Inspection · CPB

May 21, 2024Administrative

Development fee collection

Building Inspection · DFCU

May 15, 2024Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$447,819
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Bonnie Louise Bridges

Studio Bba

ArchitectC23785
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202305238412 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record