1500 A Jerrold Av
San Francisco permit 202305248534 · Bayview Hunters Point
New 2 bedroom attached adu remodel with addition, new kitchen, new plumbing, electrical & mechanical.
- Filed
- May 24, 2023
- Issued
- Apr 17, 2025 (23 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 22 stops across 4 departments
- Comments issued
- 3 times, by Building Inspection
- Put on hold
- Once
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 24, 2023 | Jun 21, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Jun 21, 2023 | Aug 15, 2023 | Approved |
Building plan review Building Inspection · BLDG | Jun 21, 2023 | Jul 6, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jun 21, 2023 | Aug 1, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jun 21, 2023 | Jun 26, 2023 | — |
Urban forestry Public Works · DPW-BUF | Jun 21, 2023 | May 23, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 21, 2023 | Jul 6, 2023 | — |
Permit Processing Center Building Inspection · PPC | Jun 21, 2023 | Dec 19, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Feb 2, 2024 | Feb 9, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 2, 2024 | Feb 6, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Feb 2, 2024 | Feb 5, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 2, 2024 | Feb 7, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 2, 2024 | Feb 9, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jul 25, 2024 | Jul 26, 2024 | Approved |
Zoning review Planning · CP-ZOC | Jul 25, 2024 | Oct 17, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jul 25, 2024 | Jul 29, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 25, 2024 | Jul 29, 2024 | Approved |
Urban forestry Public Works · DPW-BUF | Jul 25, 2024 | Aug 20, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 25, 2024 | Aug 1, 2024 | Approved |
Zoning review Planning · CP-ZOC | Oct 21, 2024 | Dec 10, 2024 | Approved |
Development fee collection Building Inspection · DFCU | Dec 11, 2024 | Dec 19, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | Dec 19, 2024 | Apr 17, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $221,276
| Name | Role | License on permit |
|---|---|---|
| Ricardo Gonzalez | Engineer | 58960 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025