2390 Bush St
San Francisco permit 202305258562 · Pacific Heights
Voluntary structural. repair work at church bell tower structural work includes replacment of carroded steel bracing which was added during the 1990 seismic rehabiltation of the church. accessiblility upgrades: signage at parking lot, restroom, restroom work. maher n/a.
- Filed
- May 25, 2023
- Issued
- Aug 18, 2023 (3 months after filing)
- Completed
- Dec 14, 2023 (4 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 9 stops across 3 departments
- Comments issued
- Once, by Building Inspection
- Put on hold
- Once
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | May 25, 2023 | May 26, 2023 | — |
Fire prevention review Fire Department · SFFD | May 25, 2023 | May 25, 2023 | — |
Central Permit Bureau Building Inspection · CPB | May 26, 2023 | Jun 9, 2023 | — |
Building plan review Building Inspection · BLDG | Jun 9, 2023 | Aug 1, 2023 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jun 9, 2023 | Jul 28, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 28, 2023 | Jul 28, 2023 | Approved |
Building plan review Building Inspection · BLDG | Aug 11, 2023 | Aug 11, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Aug 14, 2023 | Aug 14, 2023 | Administrative |
Central Permit Bureau Building Inspection · CPB | Aug 14, 2023 | Aug 18, 2023 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $1,185,000
| Name | Role | License on permit |
|---|---|---|
| Peter J Birkholz Page & Turnbull | Architect | C23418 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2025