2527 25th St
San Francisco permit 202305258595 · Mission
Convert existing ground level non-conforming unit and garage to 2-bedroom/ 1-bath adu: 708 sqft, per ordinance # 162-16. existing non-conforming adu will be added per government code section 65852.2.
- Filed
- May 25, 2023
- Issued
- Nov 6, 2024 (17 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 49 stops across 5 departments
- Comments issued
- 25 times, by Planning, Building Inspection, Fire Department, Public Works, Public Utilities
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 25, 2023 | Jan 30, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Jan 30, 2024 | Feb 13, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Jan 30, 2024 | Feb 8, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jan 30, 2024 | Feb 14, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jan 30, 2024 | Feb 7, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jan 30, 2024 | Feb 6, 2024 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Jan 30, 2024 | May 28, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jan 30, 2024 | Feb 5, 2024 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Jan 30, 2024 | Oct 22, 2024 | Administrative |
Zoning review Planning · CP-ZOC | May 6, 2024 | May 23, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | May 6, 2024 | May 8, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | May 6, 2024 | May 20, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | May 6, 2024 | May 9, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | May 6, 2024 | May 14, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 6, 2024 | May 7, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | May 15, 2024 | May 23, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | May 15, 2024 | May 20, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | May 15, 2024 | May 16, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jun 10, 2024 | Jun 10, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Jul 11, 2024 | Jul 23, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jul 11, 2024 | Jul 22, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jul 11, 2024 | Jul 24, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jul 11, 2024 | Jul 16, 2024 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Jul 11, 2024 | Jul 24, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 11, 2024 | Jul 16, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jul 11, 2024 | Jul 11, 2024 | Approved |
Building plan review Building Inspection · BLDG | Aug 13, 2024 | Aug 28, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 13, 2024 | Aug 26, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Aug 13, 2024 | Aug 15, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Aug 13, 2024 | Aug 13, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Aug 13, 2024 | Aug 20, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 13, 2024 | Aug 14, 2024 | Approved |
Urban forestry Public Works · DPW-BUF | Aug 13, 2024 | Aug 23, 2024 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Aug 22, 2024 | Aug 22, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Aug 23, 2024 | Aug 28, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Aug 23, 2024 | Aug 29, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Aug 23, 2024 | Aug 26, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 23, 2024 | Aug 26, 2024 | Approved |
Urban forestry Public Works · DPW-BUF | Aug 23, 2024 | Sep 26, 2024 | Approved-Stipulated |
Building plan review Building Inspection · BLDG | Aug 29, 2024 | Sep 4, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Aug 29, 2024 | Aug 30, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 29, 2024 | Sep 4, 2024 | Approved |
Zoning review Planning · CP-ZOC | Aug 29, 2024 | Sep 5, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 29, 2024 | Sep 13, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 29, 2024 | Aug 29, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 4, 2024 | Sep 4, 2024 | Approved |
Zoning review Planning · CP-ZOC | Oct 1, 2024 | Oct 22, 2024 | Approved |
Development fee collection Building Inspection · DFCU | Oct 22, 2024 | Oct 22, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | Oct 22, 2024 | Nov 6, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $135,228
| Name | Role | License on permit |
|---|---|---|
| Ahsanullah Kushkaki | Architect | C59045 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2025