237 Hartford St
San Francisco permit 202305268680 · Castro/Upper Market
Interior/exterior renovation of an (e)2 unit,wood framed residence,including reinforcement of(e)brick foundations & seismic stiffening.new kitchens,plumbing upgrades,electrical upgrades, new fixtures, (n)moment frames,garage/basement beams to replace column obstructions, (n) rear yard patio to allow
- Filed
- May 26, 2023
- Issued
- Jan 21, 2026 (32 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 35 stops across 4 departments
- Comments issued
- 7 times, by Building Inspection, Public Works, Public Utilities, Planning
- Put on hold
- Once
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 26, 2023 | Aug 31, 2023 | Administrative |
Planning neighborhood notice Planning · CP-NP | Jun 7, 2023 | Jun 14, 2023 | — |
Zoning review Planning · CP-ZOC | Aug 31, 2023 | Sep 18, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Aug 31, 2023 | Mar 13, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Sep 19, 2023 | Nov 3, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Sep 19, 2023 | Oct 25, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 19, 2023 | Sep 20, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Sep 19, 2023 | Oct 13, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Oct 31, 2023 | Oct 31, 2023 | Approved |
Building plan review Building Inspection · BLDG | Jul 5, 2024 | Jul 18, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jul 5, 2024 | Jul 8, 2024 | Approved |
Zoning review Planning · CP-ZOC | Jul 5, 2024 | Jul 9, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jul 5, 2024 | Jul 15, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 5, 2024 | Jul 11, 2024 | Approved |
Building plan review Building Inspection · BLDG | Sep 30, 2024 | Oct 17, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Sep 30, 2024 | Oct 2, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 30, 2024 | Oct 16, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 30, 2024 | Oct 1, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 30, 2024 | Oct 3, 2024 | Approved |
Building plan review Building Inspection · BLDG | Dec 17, 2024 | Jan 9, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Dec 17, 2024 | Dec 17, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Dec 17, 2024 | Jan 8, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 17, 2024 | Dec 26, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 17, 2024 | Dec 19, 2024 | Approved |
Building plan review Building Inspection · BLDG | Feb 3, 2025 | Feb 3, 2025 | Approved |
Zoning review Planning · CP-ZOC | Feb 3, 2025 | Feb 6, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 3, 2025 | Feb 19, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 3, 2025 | Feb 5, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 3, 2025 | Feb 5, 2025 | Approved |
Zoning review Planning · CP-ZOC | Feb 21, 2025 | Feb 24, 2025 | Approved |
Building plan review Building Inspection · BLDG | Feb 21, 2025 | Feb 26, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 21, 2025 | Mar 12, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 21, 2025 | Feb 24, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 21, 2025 | Feb 24, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 13, 2025 | Jan 21, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $1,250,000
| Name | Role | License on permit |
|---|---|---|
| Andrew J Dunbar Interstice Architects | Architect | C28143 |
| David M Strandberg Strandberg Engineering | Engineer | 62993 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025