3240 25th St
San Francisco permit 202305318873 · Mission
Addition to level 1. work to include 2 (n) bedrooms, bath, and laundry closet at level 1. (n) roof deck at level 2.
- Filed
- May 31, 2023
- Issued
- Apr 3, 2024 (10 months after filing)
- Completed
- Jun 10, 2026 (26 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 27 stops across 5 departments
- Comments issued
- 6 times, by Building Inspection, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 31, 2023 | Jun 1, 2023 | — |
Zoning review Planning · CP-ZOC | Jun 1, 2023 | Aug 14, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Jun 1, 2023 | Mar 29, 2024 | — |
Planning neighborhood notice Planning · CP-NP | Jun 23, 2023 | Jun 30, 2023 | Approved |
Building plan review Building Inspection · BLDG | Aug 17, 2023 | Sep 12, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 17, 2023 | Sep 6, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Aug 17, 2023 | Aug 24, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Aug 17, 2023 | Aug 21, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 13, 2023 | Sep 13, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Sep 18, 2023 | Dec 8, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 6, 2023 | Dec 6, 2023 | Approved |
Building plan review Building Inspection · BLDG | Dec 8, 2023 | Dec 11, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Dec 8, 2023 | Dec 8, 2023 | Issued Comments |
Zoning review Planning · CP-ZOC | Dec 8, 2023 | Dec 8, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 8, 2023 | Jan 5, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Dec 20, 2023 | Dec 20, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Dec 20, 2023 | Jan 8, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Dec 20, 2023 | Mar 11, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Dec 27, 2023 | Dec 27, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 28, 2024 | Feb 28, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Mar 5, 2024 | Mar 5, 2024 | Approved |
Zoning review Planning · CP-ZOC | Mar 18, 2024 | Mar 19, 2024 | Approved |
Building plan review Building Inspection · BLDG | Mar 18, 2024 | Mar 25, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 18, 2024 | Mar 25, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 18, 2024 | Mar 27, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Mar 18, 2024 | Mar 29, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 29, 2024 | Apr 3, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $162,000
| Name | Role | License on permit |
|---|---|---|
| Jason Park Langkammerer At6 Architecture | Architect | C28796 |
| Nate Williams Gi Paoleth Design Lab | Engineer | C62068 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jun 2021