501 Post St
San Francisco permit 202306059201 · Tenderloin
Provide 2 accessible vehicle pull-up space with passenger drop-off & loading zone. upgrade and provide accessible path of travel from the public site walk and vehicle drop-off & loading zones to the building lobby. new concrete paving. new accessible ramp. new accessible curb cut ramp. new striping
- Filed
- Jun 5, 2023
- Issued
- Apr 30, 2026 (35 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 19 stops across 4 departments
- Comments issued
- 3 times, by Building Inspection
- Put on hold
- Once
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jun 5, 2023 | Jun 6, 2023 | — |
Zoning review Planning · CP-ZOC | Jun 6, 2023 | Jun 21, 2023 | — |
Permit Processing Center Building Inspection · PPC | Jun 6, 2023 | Apr 3, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Jun 22, 2023 | Aug 8, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jun 22, 2023 | Jun 28, 2023 | — |
Fire prevention review Fire Department · SFFD | Jul 24, 2023 | Sep 21, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Oct 24, 2023 | Oct 25, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Nov 6, 2023 | Nov 6, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 7, 2023 | Dec 4, 2023 | Approved |
Zoning review Planning · CP-ZOC | Feb 10, 2026 | Feb 11, 2026 | Approved |
Building plan review Building Inspection · BLDG | Feb 10, 2026 | Feb 17, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Feb 10, 2026 | Feb 19, 2026 | Approved |
Zoning review Planning · CP-ZOC | Mar 20, 2026 | Mar 23, 2026 | Approved |
Building plan review Building Inspection · BLDG | Mar 20, 2026 | Mar 26, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 20, 2026 | Mar 23, 2026 | Approved |
Zoning review Planning · CP-ZOC | Mar 27, 2026 | Mar 30, 2026 | Approved |
Building plan review Building Inspection · BLDG | Mar 27, 2026 | Mar 27, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 27, 2026 | Mar 30, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 3, 2026 | Apr 30, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $150,000
| Name | Role | License on permit |
|---|---|---|
| Scott Bernard Sullivan Relativity Architects | Architect | C33139 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026