As written on the permit application.

Change of use to establish f-1 occupancy, light manufacturing for non/voc/nonvolatile cannabis manufacturing, wholesale sales use for cannabis distribution, continuation of (e) industrial agriculture use for cannabis cultivation.

Timeline
Key dates from the city record.
Filed
Jun 7, 2023
Issued
Dec 22, 2023 (7 months after filing)
Completed
Dec 17, 2024 (12 months after issuance)

For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
16 stops across 6 departments
Comments issued
Once, by Fire Department
Review stopFinishedResult

Intake

Building Inspection · INTAKE

Jun 7, 2023—

Building inspector

Building Inspection · BID-INSP

Jun 7, 2023—

Electrical inspector

Building Inspection · EID-INSP

Jun 7, 2023—

Zoning review

Planning · CP-ZOC

Nov 29, 2023Approved

Intake

Building Inspection · INTAKE

Dec 4, 2023Administrative

Building plan review

Building Inspection · BLDG

Dec 4, 2023Approved

Mechanical and energy plan review

Building Inspection · MECH

Dec 4, 2023Approved

Fire prevention review

Fire Department · SFFD

Dec 4, 2023Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Dec 4, 2023Administrative

Public health review

Public Health · HEALTH

Dec 4, 2023Administrative

Permit Center

Permit Center · PERMIT-CTR

Dec 4, 2023—

Central Permit Bureau

Building Inspection · CPB

Dec 5, 2023Administrative

Fire prevention review

Fire Department · SFFD

Dec 20, 2023Approved

Permit Processing Center

Building Inspection · PPC

Dec 20, 2023Administrative

Central Permit Bureau

Building Inspection · CPB

Dec 22, 2023Administrative

Development fee collection

Building Inspection · DFCU

Dec 21, 2023Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$1
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Kyle Tamar Brunel

Pencil Box Architects

ArchitectC35905
Harvey J Hacker

Harvey Hacker Architects

ArchitectC8520
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202306079425 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record