San Francisco permit 202306079505 · Mission

ADUFull plan reviewComplete
Street view · Mar 2025
Google Street View of 849 A Dolores St, Mar 2025
Scope of work
As written on the permit application.

Conversion of addition to existing 527 sf family room & bath to become a 550 sf adu unit per oridinance 95-17.

Timeline
Key dates from the city record.
Filed
Jun 7, 2023
Issued
Dec 1, 2023 (6 months after filing)
Completed
Jul 15, 2024 (7 months after issuance)

For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
26 stops across 5 departments
Comments issued
4 times, by Planning, Public Works
Put on hold
3 times
Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Jun 27, 2023Administrative

Zoning review

Planning · CP-ZOC

Aug 2, 2023Issued Comments

Building plan review

Building Inspection · BLDG

Jul 27, 2023Approved

Mechanical and energy plan review

Building Inspection · MECH

Aug 1, 2023Approved

Fire prevention review

Fire Department · SFFD

Jul 19, 2023Approved

Street use and mapping

Public Works · DPW-BSM

Jun 29, 2023—

Urban forestry

Public Works · DPW-BUF

Aug 2, 2023Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Jul 10, 2023—

Permit Processing Center

Building Inspection · PPC

Oct 10, 2023Administrative

Street use and mapping

Public Works · DPW-BSM

Jul 20, 2023—

Public Utilities Commission review

Public Utilities · SFPUC

Aug 1, 2023Approved

Street use and mapping

Public Works · DPW-BSM

Jul 27, 2023Approved

Urban forestry

Public Works · DPW-BUF

Aug 21, 2023Issued Comments

Zoning review

Planning · CP-ZOC

Aug 30, 2023Issued Comments

Urban forestry

Public Works · DPW-BUF

Sep 12, 2023Approved

Building plan review

Building Inspection · BLDG

Aug 29, 2023Approved

Mechanical and energy plan review

Building Inspection · MECH

Sep 6, 2023Approved

Street use and mapping

Public Works · DPW-BSM

Aug 29, 2023Approved

Public Utilities Commission review

Public Utilities · SFPUC

Aug 30, 2023Approved

Zoning review

Planning · CP-ZOC

Sep 5, 2023Approved

Building plan review

Building Inspection · BLDG

Sep 11, 2023Approved

Street use and mapping

Public Works · DPW-BSM

Sep 5, 2023Approved

Public Utilities Commission review

Public Utilities · SFPUC

Sep 1, 2023Approved

Zoning review

Planning · CP-ZOC

Oct 5, 2023Approved

Development fee collection

Building Inspection · DFCU

Oct 5, 2023Administrative

Central Permit Bureau

Building Inspection · CPB

Dec 1, 2023Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$150,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Mahya Salehi FadardiArchitectC38610
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202306079505 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record