335 27th St
San Francisco permit 202306099741 · Noe Valley
Comply w/nov#202182998.-rear structure-provide a space heating system for the proposed provide kitchen throught the additon of an oven, hood& vent.replace the studio alternating tread device w/ a compliant staircase. replace driveway(e)driveway of the main residence.ordinance #95-17(add 1 state adu)
- Filed
- Jun 9, 2023
- Issued
- Mar 25, 2025 (22 months after filing)
- Completed
- Jan 7, 2026 (9 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 46 stops across 5 departments
- Comments issued
- 10 times, by Planning, Building Inspection, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jun 9, 2023 | Jun 9, 2023 | — |
Code enforcement Building Inspection · CES | Jun 22, 2023 | Jun 22, 2023 | — |
Building inspector Building Inspection · BID-INSP | Jun 26, 2023 | Jun 26, 2023 | — |
Zoning review Planning · CP-ZOC | Jul 31, 2023 | Aug 24, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Jul 31, 2023 | Aug 8, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jul 31, 2023 | Sep 5, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jul 31, 2023 | Aug 3, 2023 | Approved |
Urban forestry Public Works · DPW-BUF | Jul 31, 2023 | Aug 3, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jul 31, 2023 | Aug 21, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Jul 31, 2023 | Jan 31, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Jun 28, 2024 | Jul 10, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jun 28, 2024 | Jun 28, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jun 28, 2024 | Jul 8, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jun 28, 2024 | Jul 8, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jun 28, 2024 | Jul 2, 2024 | Approved |
Urban forestry Public Works · DPW-BUF | Jun 28, 2024 | Sep 9, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 28, 2024 | Jul 15, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 15, 2024 | Jul 15, 2024 | Approved |
Building plan review Building Inspection · BLDG | Aug 22, 2024 | Aug 26, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Aug 22, 2024 | Sep 4, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 22, 2024 | Aug 28, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Aug 22, 2024 | Aug 22, 2024 | Approved |
Zoning review Planning · CP-ZOC | Aug 22, 2024 | Aug 22, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 22, 2024 | Aug 23, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 22, 2024 | Aug 23, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 30, 2024 | Aug 30, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Oct 25, 2024 | Nov 4, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Oct 25, 2024 | Oct 25, 2024 | Approved |
Building plan review Building Inspection · BLDG | Oct 25, 2024 | Oct 30, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 25, 2024 | Nov 7, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Oct 25, 2024 | Oct 28, 2024 | Approved |
Urban forestry Public Works · DPW-BUF | Oct 25, 2024 | Nov 21, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Oct 25, 2024 | Oct 28, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 25, 2024 | Oct 28, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Nov 15, 2024 | Nov 15, 2024 | Approved |
Zoning review Planning · CP-ZOC | Nov 15, 2024 | Nov 18, 2024 | Approved |
Building plan review Building Inspection · BLDG | Nov 15, 2024 | Nov 20, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Nov 15, 2024 | Nov 20, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Nov 15, 2024 | Nov 18, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 15, 2024 | Nov 18, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 15, 2024 | Nov 22, 2024 | Approved |
Zoning review Planning · CP-ZOC | Jan 13, 2025 | Jan 13, 2025 | Approved |
Development fee collection Building Inspection · DFCU | Jan 13, 2025 | Jan 13, 2025 | Administrative |
Building inspector Building Inspection · BID-INSP | Jan 13, 2025 | Jan 31, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 31, 2025 | Mar 25, 2025 | Administrative |
Central Permit Bureau Building Inspection · CPB | Feb 4, 2025 | Mar 25, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $122,000
| Name | Role | License on permit |
|---|---|---|
| Edward Davis Morris Kerman Morris Architects | Architect | C24585 |
| Rodrigo Santos Rs Engineering | Engineer | S2984 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2022