161 Delano Av
San Francisco permit 202306129772 · Outer Mission
Condition basement space, w/a tall ceiling into liveable space2 bedrooms, shearlwall retrofit for basement; relocate laundry, 2 exterior doors, tiny addition for the staircase expansion, ac furnace - new; pg&e panel relocate to the outside flip at the same location
- Filed
- Jun 12, 2023
- Issued
- Oct 23, 2023 (4 months after filing)
- Completed
- Sep 3, 2024 (10 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2023 were typically issued within 1 month (median of 4,704 issued permits).
- Review stops
- 17 stops across 3 departments
- Comments issued
- None
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Jun 12, 2023 | Jun 12, 2023 | — |
Zoning review Planning · CP-ZOC | Jun 12, 2023 | Jun 12, 2023 | — |
Intake Building Inspection · INTAKE | Jul 17, 2023 | Jul 17, 2023 | — |
Zoning review Planning · CP-ZOC | Jul 17, 2023 | Jul 17, 2023 | — |
Intake Building Inspection · INTAKE | Aug 7, 2023 | Aug 7, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Aug 7, 2023 | Aug 7, 2023 | Approved |
Intake Building Inspection · INTAKE | Aug 21, 2023 | Aug 21, 2023 | Administrative |
Intake Building Inspection · INTAKE | Sep 6, 2023 | Sep 6, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Sep 6, 2023 | Sep 6, 2023 | Approved |
Intake Building Inspection · INTAKE | Oct 4, 2023 | Oct 4, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Oct 4, 2023 | Oct 4, 2023 | Approved |
Intake Building Inspection · INTAKE | Oct 18, 2023 | Oct 18, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Oct 18, 2023 | Oct 18, 2023 | Approved |
Building plan review Building Inspection · BLDG | Oct 18, 2023 | Oct 18, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 18, 2023 | Oct 18, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 18, 2023 | Oct 23, 2023 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Oct 23, 2023 | Oct 23, 2023 | Approved |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $200,000
| Name | Role | License on permit |
|---|---|---|
| Romain Curtis Romain Curtis Architect | Architect | C35019 |
| Francis Malkham Design Everest Consulting | Engineer | C76860 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025