280 South Van Ness Av
San Francisco permit 202306139974 · Mission
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
Revision to bpa#202201266271. onsite dry utility install & associated trenching.
- Filed
- Jun 13, 2023
- Issued
- Jun 21, 2023 (within 1 month of filing)
- Completed
- Mar 5, 2024 (8 months after issuance)
- Review stops
- 6 stops across 3 departments
- Comments issued
- Not recorded for this permit
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Jun 13, 2023 | Jun 13, 2023 | — |
Intake Building Inspection · INTAKE | Jun 14, 2023 | Jun 14, 2023 | — |
Zoning review Planning · CP-ZOC | Jun 14, 2023 | Jun 14, 2023 | — |
Building plan review Building Inspection · BLDG | Jun 14, 2023 | Jun 14, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jun 14, 2023 | Jun 14, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Jun 21, 2023 | Jun 21, 2023 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $10,250
| Name | Role | License on permit |
|---|---|---|
| Alan Arthur Cross Proto Inc. | Architect | C30029 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jun 2016