2828 Vallejo St
San Francisco permit 202306200459 · Pacific Heights
Increasing sf of subbasement level, reconfigure interior & lower floor 6'8". increase sf of basement level. reconfifure interior & lower fl 2'-6'2".
- Filed
- Jun 20, 2023
- Issued
- Jan 12, 2024 (7 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 20 stops across 4 departments
- Comments issued
- 4 times, by Public Works, Building Inspection, Public Utilities
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Jun 20, 2023 | Jun 20, 2023 | — |
Zoning review Planning · CP-ZOC | Jun 21, 2023 | Jun 21, 2023 | — |
Intake Building Inspection · INTAKE | Jul 19, 2023 | Jul 19, 2023 | — |
Zoning review Planning · CP-ZOC | Aug 2, 2023 | Aug 2, 2023 | Approved |
Building plan review Building Inspection · BLDG | Aug 11, 2023 | Aug 11, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Aug 11, 2023 | Aug 11, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 15, 2023 | Aug 15, 2023 | Issued Comments |
Central Permit Bureau Building Inspection · CPB | Aug 18, 2023 | Aug 24, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Aug 24, 2023 | Oct 12, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Oct 18, 2023 | Oct 20, 2023 | Administrative |
Public Utilities Commission review Public Utilities · SFPUC | Oct 18, 2023 | Oct 24, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Nov 15, 2023 | Nov 15, 2023 | Approved |
Building plan review Building Inspection · BLDG | Dec 1, 2023 | Dec 8, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Dec 18, 2023 | Dec 18, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 18, 2023 | Dec 20, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Dec 22, 2023 | Dec 27, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 27, 2023 | Dec 28, 2023 | Approved |
Zoning review Planning · CP-ZOC | Dec 28, 2023 | Jan 4, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Jan 9, 2024 | Jan 9, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | Jan 9, 2024 | Jan 12, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $2,450,000
| Name | Role | License on permit |
|---|---|---|
| Suzette Anne Smith | Architect | C30980 |
| Nikica Favretto Ftf Engineering | Engineer | 83339 |
| Jillian Van Enckevort Ftf Engineering | Engineer | S-5394 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2015