38 Eastman St #0
San Francisco permit 202306230725 · Russian Hill
Rebuild (e) garage and roof deck on top. modify foot print to accomodate (e) tree. replace (e) garage door, replace (e) front door rebuild garage face. extend 1" to north property line
- Filed
- Jun 23, 2023
- Issued
- Apr 11, 2024 (10 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2023 were typically issued within 1 month (median of 4,704 issued permits).
- Review stops
- 10 stops across 4 departments
- Comments issued
- None
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Jun 23, 2023 | Jun 23, 2023 | — |
Zoning review Planning · CP-ZOC | Jun 23, 2023 | Jun 23, 2023 | — |
Zoning review Planning · CP-ZOC | Feb 14, 2024 | Feb 14, 2024 | Approved |
Building plan review Building Inspection · BLDG | Apr 2, 2024 | Apr 2, 2024 | Not Applicable |
Building plan review Building Inspection · BLDG | Apr 2, 2024 | Apr 2, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Apr 9, 2024 | Apr 9, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 9, 2024 | Apr 9, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Apr 9, 2024 | Apr 9, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 9, 2024 | Apr 9, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 11, 2024 | Apr 11, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Issued
- Estimated cost
- $150,000
| Name | Role | License on permit |
|---|---|---|
| Luke Caspar Ogrydziak Ogrydziak Prillinger Arch | Architect | C29338 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2019