414 Brannan St
San Francisco permit 202306230779 · South of Market
Seismic retrofit of 3-story + basement, commercial building. interior remodel including restroom, elevator & path of travel upgrades. no exterior work
- Filed
- Jun 23, 2023
- Issued
- Mar 22, 2024 (9 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 23 stops across 4 departments
- Comments issued
- 5 times, by Building Inspection
- Put on hold
- Once
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Jun 23, 2023 | Jun 23, 2023 | — |
Building plan review Building Inspection · BLDG | Jun 27, 2023 | Jun 27, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jul 3, 2023 | Jul 11, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jul 11, 2023 | Jul 11, 2023 | — |
Permit Center Permit Center · PERMIT-CTR | Jul 11, 2023 | Jul 11, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jul 11, 2023 | Jul 13, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Jul 11, 2023 | Jul 17, 2023 | — |
Building pre-screening Building Inspection · PRE-BLDG | Jul 17, 2023 | Jul 17, 2023 | — |
Structural plan approval Building Inspection · PAD-STR | Jul 17, 2023 | Aug 29, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Oct 3, 2023 | Jan 22, 2024 | Issued Comments |
Central Permit Bureau Building Inspection · CPB | Nov 30, 2023 | Nov 30, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Nov 30, 2023 | Jan 31, 2024 | Administrative |
Structural plan approval Building Inspection · PAD-STR | Nov 30, 2023 | Jan 4, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Nov 30, 2023 | Dec 4, 2023 | Approved-Stipulated |
Permit Processing Center Building Inspection · PPC | Nov 30, 2023 | Mar 13, 2024 | — |
Zoning review Planning · CP-ZOC | Dec 7, 2023 | Dec 11, 2023 | Approved |
Building plan review Building Inspection · BLDG | Jan 18, 2024 | Jan 29, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jan 26, 2024 | Jan 26, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Feb 21, 2024 | Mar 5, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Feb 27, 2024 | Mar 5, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 7, 2024 | Mar 13, 2024 | Approved |
Zoning review Planning · CP-ZOC | Mar 7, 2024 | Mar 11, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 13, 2024 | Mar 22, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $1,975,000
| Name | Role | License on permit |
|---|---|---|
| Ana C Quezada Quezada Architecture Inc | Architect | C25871 |
| Scott Fine Arnold Fyfe Engineering | Engineer | C-64169 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026