1997 14th Av
San Francisco permit 202306270942 · Inner Sunset
Interior remodel: replace windows, repair water damage to exterior finishes. replace hot water heater and hvac heat pump. reduce rear deck. 2 bathrooms & 1 kitchen remodeling and all interior rooms.
- Filed
- Jun 27, 2023
- Issued
- Jun 3, 2024 (11 months after filing)
- Completed
- Jan 29, 2026 (20 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 24 stops across 5 departments
- Comments issued
- 7 times, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Jun 27, 2023 | Jun 27, 2023 | — |
Zoning review Planning · CP-ZOC | Jun 27, 2023 | Jun 27, 2023 | — |
Intake Building Inspection · INTAKE | Aug 4, 2023 | Aug 4, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Aug 4, 2023 | Aug 4, 2023 | Approved |
Permit Center Permit Center · PERMIT-CTR | Sep 1, 2023 | Sep 1, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Sep 6, 2023 | Oct 20, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Oct 20, 2023 | Dec 6, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Dec 8, 2023 | Jan 3, 2024 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Jan 3, 2024 | Jan 8, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 8, 2024 | Jan 9, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 10, 2024 | Jan 29, 2024 | Approved |
Building plan review Building Inspection · BLDG | Mar 13, 2024 | Mar 13, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Apr 5, 2024 | Apr 5, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Apr 19, 2024 | Apr 19, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Apr 19, 2024 | Apr 22, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | May 2, 2024 | May 2, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | May 10, 2024 | May 10, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 10, 2024 | May 16, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 16, 2024 | May 16, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | May 16, 2024 | May 20, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 20, 2024 | May 21, 2024 | Approved |
Zoning review Planning · CP-ZOC | May 21, 2024 | May 22, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | May 23, 2024 | May 28, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | May 28, 2024 | Jun 3, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $270,000
| Name | Role | License on permit |
|---|---|---|
| Earle Edward Weiss E.E. Weiss Architects, Inc. | Architect | C22416 |
| David W Kane Harrell Kane S.E. Inc. | Engineer | S-5278 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2017