157 Laidley St
San Francisco permit 202306281044 · Glen Park
Renovation project includes new rear addition, finished basement level, resulting in a home with 5 bedrooms and 3.5 bathrooms.
- Filed
- Jun 28, 2023
- Issued
- Dec 6, 2024 (17 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 50 stops across 6 departments
- Comments issued
- 17 times, by Building Inspection, Public Utilities, Fire Department, Public Works
- Put on hold
- Once
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jun 28, 2023 | Jul 6, 2023 | — |
Zoning review Planning · CP-ZOC | Jul 6, 2023 | Aug 31, 2023 | Administrative |
Permit Processing Center Building Inspection · PPC | Jul 6, 2023 | Nov 13, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Aug 31, 2023 | Apr 11, 2024 | Approved |
Building plan review Building Inspection · BLDG | Apr 11, 2024 | May 7, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Apr 11, 2024 | Apr 15, 2024 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Apr 11, 2024 | Apr 23, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Apr 26, 2024 | Apr 26, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | May 2, 2024 | Jun 28, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Jul 5, 2024 | Jul 8, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jul 5, 2024 | Jul 15, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Jul 5, 2024 | Jul 9, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 5, 2024 | Jul 10, 2024 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Jul 5, 2024 | Jul 17, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Jul 9, 2024 | Jul 18, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Jul 24, 2024 | Jul 25, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jul 24, 2024 | Jul 29, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jul 24, 2024 | Aug 20, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jul 24, 2024 | Jul 24, 2024 | Approved-Stipulated |
Zoning review Planning · CP-ZOC | Jul 24, 2024 | Jul 24, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 24, 2024 | Jul 25, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Oct 1, 2024 | Oct 2, 2024 | Approved |
Zoning review Planning · CP-ZOC | Oct 2, 2024 | Oct 2, 2024 | Approved |
Building plan review Building Inspection · BLDG | Oct 18, 2024 | Oct 18, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Nov 5, 2024 | Nov 5, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 7, 2024 | Nov 13, 2024 | Approved-Stipulated |
Development fee collection Building Inspection · DFCU | Nov 13, 2024 | Nov 13, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | Nov 13, 2024 | Dec 6, 2024 | Administrative |
Addendum 1: Final plans: arch mep
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | May 20, 2026 | Jun 10, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 10, 2026 | Jun 12, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Jun 12, 2026 | Jun 18, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jun 12, 2026 | Aug 21, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jun 12, 2026 | Aug 21, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jun 12, 2026 | Jul 7, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jun 12, 2026 | Jun 18, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Jun 12, 2026 | Jun 18, 2026 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Jun 12, 2026 | Jul 24, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jun 12, 2026 | Jun 23, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Jun 12, 2026 | In progress | — |
Fire prevention review Fire Department · SFFD | Oct 15, 2026 | Oct 16, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 16, 2026 | Oct 16, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 19, 2026 | Oct 19, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Oct 28, 2026 | Oct 29, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Oct 28, 2026 | Oct 29, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | — | In progress | — |
Structural plan approval Building Inspection · PAD-STR | — | In progress | — |
Mechanical and energy plan review Building Inspection · MECH | — | In progress | — |
Street use and mapping Public Works · DPW-BSM | — | In progress | — |
Urban forestry Public Works · DPW-BUF | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $1,226,000
| Name | Role | License on permit |
|---|---|---|
| Geoffrey Gibson Winder Gison Architects | Architect | C35924 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2021