San Francisco permit 202306281044 · Glen Park

AdditionFull plan reviewIssued
Street view · Feb 2021
Google Street View of 157 Laidley St, Feb 2021
Scope of work
As written on the permit application.

Renovation project includes new rear addition, finished basement level, resulting in a home with 5 bedrooms and 3.5 bathrooms.

Timeline
Key dates from the city record.
Filed
Jun 28, 2023
Issued
Dec 6, 2024 (17 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
50 stops across 6 departments
Comments issued
17 times, by Building Inspection, Public Utilities, Fire Department, Public Works
Put on hold
Once

Main permit

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Jul 6, 2023—

Zoning review

Planning · CP-ZOC

Aug 31, 2023Administrative

Permit Processing Center

Building Inspection · PPC

Nov 13, 2024Administrative

Zoning review

Planning · CP-ZOC

Apr 11, 2024Approved

Building plan review

Building Inspection · BLDG

May 7, 2024Issued Comments

Street use and mapping

Public Works · DPW-BSM

Apr 15, 2024Approved-Stipulated

Public Utilities Commission review

Public Utilities · SFPUC

Apr 23, 2024Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Apr 26, 2024Approved

Structural plan approval

Building Inspection · PAD-STR

Jun 28, 2024Issued Comments

Building plan review

Building Inspection · BLDG

Jul 8, 2024Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Jul 15, 2024Issued Comments

Zoning review

Planning · CP-ZOC

Jul 9, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Jul 10, 2024Approved-Stipulated

Public Utilities Commission review

Public Utilities · SFPUC

Jul 17, 2024Approved

Fire prevention review

Fire Department · SFFD

Jul 18, 2024Issued Comments

Building plan review

Building Inspection · BLDG

Jul 25, 2024Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Jul 29, 2024Issued Comments

Fire prevention review

Fire Department · SFFD

Aug 20, 2024Issued Comments

Street use and mapping

Public Works · DPW-BSM

Jul 24, 2024Approved-Stipulated

Zoning review

Planning · CP-ZOC

Jul 24, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jul 25, 2024Approved

Fire prevention review

Fire Department · SFFD

Oct 2, 2024Approved

Zoning review

Planning · CP-ZOC

Oct 2, 2024Approved

Building plan review

Building Inspection · BLDG

Oct 18, 2024Approved

Structural plan approval

Building Inspection · PAD-STR

Nov 5, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Nov 13, 2024Approved-Stipulated

Development fee collection

Building Inspection · DFCU

Nov 13, 2024Administrative

Central Permit Bureau

Building Inspection · CPB

Dec 6, 2024Administrative

Addendum 1: Final plans: arch mep

Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Jun 10, 2026Approved

Central Permit Bureau

Building Inspection · CPB

Jun 12, 2026Administrative

Zoning review

Planning · CP-ZOC

Jun 18, 2026Approved

Building plan review

Building Inspection · BLDG

Aug 21, 2026Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Aug 21, 2026Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Jul 7, 2026Issued Comments

Fire prevention review

Fire Department · SFFD

Jun 18, 2026Approved

Street use and mapping

Public Works · DPW-BSM

Jun 18, 2026Issued Comments

Urban forestry

Public Works · DPW-BUF

Jul 24, 2026Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Jun 23, 2026Approved

Permit Processing Center

Building Inspection · PPC

In progress—

Fire prevention review

Fire Department · SFFD

Oct 16, 2026Approved

Public Utilities Commission review

Public Utilities · SFPUC

Oct 16, 2026Approved

Mechanical and energy plan review

Building Inspection · MECH

Oct 19, 2026Issued Comments

Building plan review

Building Inspection · BLDG

Oct 29, 2026Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Oct 29, 2026Issued Comments

Building plan review

Building Inspection · BLDG

In progress—

Structural plan approval

Building Inspection · PAD-STR

In progress—

Mechanical and energy plan review

Building Inspection · MECH

In progress—

Street use and mapping

Public Works · DPW-BSM

In progress—

Urban forestry

Public Works · DPW-BUF

In progress—

Central Permit Bureau

Building Inspection · CPB

In progress—

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$1,226,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Geoffrey Gibson

Winder Gison Architects

ArchitectC35924
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202306281044 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record