2765 Filbert St
San Francisco permit 202306281080 · Marina
Remodel kitchen, 2 bathrooms & interior space.
- Filed
- Jun 28, 2023
- Issued
- Mar 25, 2024 (9 months after filing)
- Completed
- Dec 5, 2025 (20 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 17 stops across 4 departments
- Comments issued
- 3 times, by Planning, Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jun 28, 2023 | Jun 28, 2023 | — |
Zoning review Planning · CP-ZOC | Jun 28, 2023 | Aug 1, 2023 | Issued Comments |
Zoning review Planning · CP-ZOC | Aug 21, 2023 | Aug 22, 2023 | Approved |
Building plan review Building Inspection · BLDG | Aug 23, 2023 | Sep 21, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Sep 21, 2023 | Nov 7, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 7, 2023 | Nov 15, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 15, 2023 | Nov 29, 2023 | Approved |
Building plan review Building Inspection · BLDG | Dec 4, 2023 | Dec 4, 2023 | Approved |
Structural plan approval Building Inspection · PAD-STR | Dec 4, 2023 | Feb 1, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Mar 6, 2024 | Mar 6, 2024 | Approved |
Building plan review Building Inspection · BLDG | Mar 6, 2024 | Mar 7, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Mar 7, 2024 | Mar 7, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 7, 2024 | Mar 11, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 12, 2024 | Mar 15, 2024 | Approved |
Zoning review Planning · CP-ZOC | Mar 15, 2024 | Mar 18, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Mar 19, 2024 | Mar 19, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | Mar 19, 2024 | Mar 25, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $386,685
| Name | Role | License on permit |
|---|---|---|
| Lisa Wai Sum Tse Integrand, Inc | Engineer | S4839 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2017