1892 V Union St
San Francisco permit 202306291209 · Marina
Upgrade (e) commercial entries per ordiance 51-16 abe programe to comply w/accessible entrance program. 1892 union: abe 201808232030 replace door, add constrast stripes to stairs, lower intercom.
- Filed
- Jun 29, 2023
- Issued
- Nov 9, 2023 (4 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2023 were typically issued within 1 month (median of 4,704 issued permits).
- Review stops
- 13 stops across 4 departments
- Comments issued
- None
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Jun 29, 2023 | Jun 29, 2023 | — |
Zoning review Planning · CP-ZOC | Jun 30, 2023 | Jun 30, 2023 | — |
Intake Building Inspection · INTAKE | Jul 7, 2023 | Jul 7, 2023 | — |
Zoning review Planning · CP-ZOC | Jul 7, 2023 | Jul 7, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 7, 2023 | Jul 7, 2023 | — |
Urban forestry Public Works · DPW-BUF | Jul 7, 2023 | Jul 7, 2023 | — |
Building plan review Building Inspection · BLDG | Jul 20, 2023 | Jul 20, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Jul 20, 2023 | Jul 20, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jul 20, 2023 | Jul 20, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jul 20, 2023 | Jul 20, 2023 | — |
Fire prevention review Fire Department · SFFD | Jul 20, 2023 | Jul 20, 2023 | — |
Intake Building Inspection · INTAKE | Oct 3, 2023 | Oct 3, 2023 | Administrative |
Central Permit Bureau Building Inspection · CPB | Nov 9, 2023 | Nov 9, 2023 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Issued
- Estimated cost
- $4,000
| Name | Role | License on permit |
|---|---|---|
| Nathan C Simpson | Architect | C-37662 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026