384 Post St
San Francisco permit 202306301252 · Financial District/South Beach
Store in store alteration to (e) commercial tenant space. install new product display fixtures and finsihes, area of work 206 sf elec scope to include telecomm and security
- Filed
- Jun 30, 2023
- Issued
- Aug 2, 2023 (1 month after filing)
- Completed
- Oct 17, 2023 (2 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2023 were typically issued within 1 month (median of 4,704 issued permits).
- Review stops
- 7 stops across 2 departments
- Comments issued
- None
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Jun 30, 2023 | Jun 30, 2023 | — |
Zoning review Planning · CP-ZOC | Jun 30, 2023 | Jun 30, 2023 | — |
Building plan review Building Inspection · BLDG | Jun 30, 2023 | Jun 30, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Jul 28, 2023 | Jul 28, 2023 | Approved |
Electrical plan review Building Inspection · MECH-E | Jul 28, 2023 | Jul 28, 2023 | Approved |
Building plan review Building Inspection · BLDG | Jul 28, 2023 | Jul 28, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 2, 2023 | Aug 2, 2023 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $75,000
| Name | Role | License on permit |
|---|---|---|
| Susanna Takfen Chan | Architect | C-38399 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026